Gantt Chart
WBS # |
Task & Subtask |
|||||||||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
|||
1 |
Planning of the project |
———— |
||||||||||
1.1 |
Analysing requirements of storage and computer infrastructure |
— |
||||||||||
1.2 |
Feasibility analysis |
— |
||||||||||
1.3 |
Analysing project risks |
— |
||||||||||
2 |
Hyper Converged Infrastructure |
———— |
||||||||||
3 |
Virtual Desktop Infrastructure |
———————— |
||||||||||
4 |
– Microsoft SQL Cluster/Farms |
———————————— |
||||||||||
4.1 |
Incorporate design, build and deployment |
————— |
||||||||||
4.2 |
Taking the design considerations |
—————— |
||||||||||
5 |
VDI Handover, Testing and Post Implementation |
————— |
||||||||||
6 |
Testing of the operations |
—— |
||||||||||
7 |
Training |
— |
||||||||||
8 |
Review of the project plan |
— |
Task & Subtask |
Milestone Status |
PV |
EV |
AC |
Variance % |
|
Schedule |
Cost |
|||||
Planning of the project |
Completed |
100 |
100 |
100 |
0 |
0 |
Analysing requirements of storage and computer infrastructure |
Completed |
25 |
25 |
25 |
0 |
0 |
Feasibility analysis |
Completed |
50 |
50 |
50 |
0 |
0 |
Analysing project risks |
Completed |
25 |
25 |
25 |
0 |
0 |
Hyper Converged Infrastructure |
Completed |
50 |
50 |
55 |
0 |
-5 |
Virtual Desktop Infrastructure |
Completed |
50 |
50 |
40 |
0 |
10 |
Microsoft SQL Cluster/Farms |
In progress |
70 |
40 |
110 |
-30 |
-70 |
Incorporate design, build and deployment |
Completed |
30 |
30 |
50 |
0 |
-10 |
Taking the design considerations |
In progress |
40 |
10 |
60 |
-30 |
-50 |
VDI Handover, Testing and Post Implementation |
Not started |
90 |
0 |
0 |
-90 |
0 |
Testing of the operations |
Not started |
40 |
0 |
0 |
-40 |
0 |
Training |
Not started |
50 |
0 |
0 |
-50 |
0 |
Review of the project plan |
Not started |
5 |
0 |
0 |
-5 |
0 |
Task Totals |
455 |
240 |
305 |
EAC = It is expected to total cost of completing all work expressed as the sum of the actual costs to date and the estimate to complete.
= $(625,000/71)
= $880281.69
The impact of cost on this particular project work is as follows:
Financial risks: The total cost for this project is $625,000 whereas the estimated cost to complete is $996,094. Therefore, the Barwon Health Project faces of financial issues due to increase into project budget.
Increase in maintenance cost: The cost required to maintain the Storage and computer infrastructure for Barwon Health Project is more as compared to assumed budget. The result is that the project faces difficulty into providing of maintenance services.
Increase into project budget: The project manager requires total budget of $996,094 to complete the plan properly with concerning all the requirements of project. The problem is that it is more than assumed budget. Due to increase into project budget, the health service faces of financial challenges.
The S-curve for Barwon Health Project is as follows:
Forecast completion date = the completion date for the project is 2nd April, 2018. It is seen that schedule baseline is required to get proper accuracy with estimation which is made for the project. The project performance is done by getting proper analysing of schedule variance which is required to estimate the project completion time. Accuracy of estimator is done by performing schedule baseline to record estimate as compared to actual outcomes.
Milestone Task |
Scheduled Completion |
Projected Completion |
Actual Completion |
Issues |
Planning and staffing project |
37 days |
37 days |
37 days |
N/A |
Hyper Converged Infrastructure |
25 days |
25 days |
25 days |
N/A |
Virtual Desktop Infrastructure |
30 days |
30 days |
30 days |
N/A |
Microsoft SQL Cluster/Farms |
50 days |
50 days |
80 days |
Extra time is required to incorporate design, build and deployment, and taking the design considerations due to improper doing of Microsoft SQL Cluster/Farms. |
VDI Handover, Testing and Post Implementation |
30 days |
30 days |
120 days |
More time is required to complete this phase as estimation into planning phase is not done properly. |
Testing of the operations |
45 days |
45 days |
85 days |
Due to increase into testing operations, extra time is required to complete this testing phase. |
Training |
15 days |
15 days |
65 days |
The workers are required more time to become familiar with development of storage and computer infrastructure. Therefore, extra time is needed to train them. |
Review of the project plan |
30 days |
30 days |
35 days |
Extra 5 days are required to review the project plan properly for meeting with client’s requirements. |
Current Problem |
Potential Impact |
Corrective Action |
Improper testing of the storage and computer infrastructure |
When there is improper testing of the storage and computer infrastructure operations, then various technical issues are raised in Barwon Health Project. |
Proper testing operations should be done so that there are no such technical challenges. |
Improper training to the staffs of health services |
Due to improper training facilities, the workers are not able to work perfectly for providing a better storage and computer infrastructure to Barwon Health Services. |
Proper training plan is done after the management team identifies the training requirements. The staffs should be trained as per required skills and expertise needed for the project. |
Improper estimation of budget |
Various financial issues are faced by Barwon Health due to increase of budget than the estimated one. |
Budget plan should be prepared to analyse the market. |
Improper implementation of Virtual Desktop Infrastructure |
Implementation of infrastructure is not properly done due to technical issues done. |
Before working into the project, implementation plan is done with consisting of various project activities. |
Part B
Project Controls Report
Project name: Barwon Health Project Tender- Storage and computer Infrastructure
Date: 10/4/2018
Project ownership: Project Manager
Prepared by: (Please fill)
Distribution list: (Please fill)
Controllable Category |
Item |
Applicable PMBOK Knowledge Area(s) |
||
1. |
Deliverables |
1.1 |
Commissioning of storage and computer infrastructure |
The commission work of the health services should be fixed as per estimated schedule and budget. |
1.2 |
Testing of the infrastructure work |
All the operations for heath project should require testing properly so that the project should complete within planned time. |
||
Proper testing plan should be implemented into the project organization. |
||||
1.3 |
Implementation of the storage and computer system |
There should be proper design, build and deployment of the virtual desktop infrastructure. |
||
There should be proper implementation of Single sign-on (SSO) into the proposed infrastructure. |
||||
2. |
Configuration |
2.1 |
Communication |
Among the project team members, there should be proper communication plan to interact with each other. |
A technical engineer is hired to configure the system properly. |
||||
2.2 |
Hardware |
A proper hardware should be selected such that configuration control to complete the process is done perfectly. |
||
All Hyper Converged hardware that comprises the solution must exist on the current VMware HCL. |
||||
2.3 |
Software |
Proper software should be selected such that configuration control to complete the process is done perfectly. |
||
The Hyper Converged system must be able to generate SNMP alerts for monitoring software. |
||||
3. |
Status accounts |
3.1 |
Work packages |
It comes under control of the accounts for the project plan. |
There should require of well planned project budget in details. |
||||
3.2 |
Planning packages |
It should consist of scope, schedule and time phased budget in details. |
||
3.3 |
Accounts planning |
There should include of work and planning packages. |
||
There should be achievement of budget backup where it is required along with project objectives. |
||||
4. |
Logs |
4.1 |
Risk register log |
A risk register along with action plan is done to mitigate the possible project risks. |
4.2 |
Team management log |
There should be proper management of team members. |
||
Stakeholder analysis is to be done properly to identify the project team members. |
||||
4.3 |
Monitoring log |
All the issues are to be monitored and captured properly. |
||
5. |
Issues |
5.1 |
Budget |
A proper budget plan is done before starting to work into the project. The project manager should estimate proper resources for the plan. |
5.2 |
Lack of communication |
Communication plan is required to interact with all the project team members. |
||
Meetings are scheduled on weekly basis to discuss the issues raised into the project. |
||||
5.3 |
Improper training |
Proper training plan is scheduled for the project so that all the unskilled employees should get proper training as per project requirements. There should be certified vendor based training for minimum x 2 technical ICT staff. |
||
Training must be provided to named staff for all aspects of Configuring and administering the Appliance, nodes and storage. |
||||
Configuration Item |
Procedural Outputs |
|||||
Configuration Control Level |
Coding System Used |
Baseline Used in this project |
Status Accounting Periodicity |
Verification and Audit Review Period and Level of Detail |
||
1.1 |
Communication |
This particular item is released. |
Infrastructure as code |
It is allocated baseline |
There is some list of change requests into the configuration items. |
14 days |
1.2 |
Hardware |
Work into progress |
Infrastructure as code |
It is functional baseline |
There is list of configuration items which are comprised of baselines. |
15 days |
1.3 |
Software |
Work into progress |
Infrastructure as code |
It is functional baseline |
There is list of configuration items which are comprised of baselines. |
10 days |
2.1 |
Contractors |
Work into progress |
Not applicable |
Others |
There is list of configuration items which are comprised of baselines. |
12 days |
2.2 |
Location |
It is uncontrolled. |
Infrastructure as code |
Others |
There is some list of change requests into the configuration items. |
15 days |
2.3 |
Documentation |
This particular item is released. |
Not applicable |
It is development baseline |
There are list of deficiencies which are being identified by the configuration baselines. |
10 days |
Controllable Category |
Item & Explanation |
PMBOK Knowledge Area |
||
Input |
Tool & Technique |
Output |
||
1. Deliverable |
1.1 Commissioning of storage and computer infrastructure |
It consist s of storage and computer infrastructure which are required to be commissioned. |
Managing of the technical stages |
There is proper commissioning of the infrastructure. |
There is proper managing of the technical stages to commission the infrastructure on proper time as the team members are taking of proper decisions to precede the health project. |
||||
1.2 Testing of the infrastructure work |
The operations which is required to test. |
Managing the technical stages |
The operations are accurately tested. |
|
There are management of the technical stages which are required to be tested properly to complete the work on time. |
||||
1.3 Implementation of the storage and computer system |
There is proper implementation of the storage and computer system. |
Balancing of the number of stages. |
There is proper implementation of the storage and computer infrastructure. |
|
Due to balancing of the stages, the cost related to implementation of infrastructure is being reduced. |
||||
2. Configuration |
2.1 Communication |
Configuration process |
End stage assessment |
Proper communication methods are used to discuss the configuration to complete the project on time. |
The end stages are identified as it is used to review the configuration to be completed. |
||||
2.2 Hardware |
Hardware system |
There are proper approval of the stages |
The hardware materials are to be configured properly. |
|
Proper approval is required from the project manager to control the items as it helps to take proper decisions to carry out the hardware configuration. |
||||
2.3 Software |
Software system |
There are proper approval of the stages |
The software materials are to be configured properly |
|
Proper approval is required from the project manager to control the items as it helps to take proper decisions to carry out the software configuration. |
||||
3. Status Accounts |
3.1 Work packages |
There are gathering of the work package items. |
End stage assessment |
Proper identification of work packages. |
The end stage assessment is used to review that work packages. |
||||
3.2 Planning packages |
There are gathering of the planning packages. |
Decision making |
Proper gathering of the planning packages. |
|
Decision making controls are used to ensure that the project should move into next step. |
||||
3.3 Accounts planning |
There is proper controlling of the plans. |
End stage assessment |
Proper controlling of the accounts plan. |
|
The end stage assessment is used to review that accounts planning. |
||||
4. Logs |
4.1 Risk register log |
Types of risks |
Decision making |
Risk register, risk management plan is required. |
Decision making is used to decide the impact, probability and impact of the project risks. |
||||
4.2 Team management log |
Proper management strategy |
Stage approval |
Proper managing of the project team |
|
Stage approval is used for managing the team to reduce time and budget delays. |
||||
4.3 Monitoring log |
Types of issues |
Monitoring control |
Monitoring of the issues accurately |
|
Monitoring control is used to control the issues to ensure whether the project is carried out properly or not. |
||||
5. Issues |
5.1 Budget |
Financial risks |
Decision making |
Proper budget plan |
Decision making is used to mitigate the financial risks and forecast proper cost for the project. |
||||
5.2 Lack of communication |
Weekly meetings |
Decision making |
Communication plan |
|
Decisions is taken to conduct weekly meetings properly. |
||||
5.3 Improper training |
Training materials |
Decision making |
Proper training programs |
|
Decisions are taken to resolve training requirement issues and the employees are trained based on required skills. |
Controllable Category |
Item & Explanation |
PMBOK Knowledge Area |
||
Input |
Tool & Technique |
Output |
||
1. Deliverable |
1.1 Commissioning of storage and computer infrastructure |
It consist s of storage and computer infrastructure which are required to be commissioned. |
Highlight reporting |
There is proper commissioning of the infrastructure. |
Highlight reporting is used for minimizing the budget requires to commission the infrastructure of Barwon Health Project. |
||||
1.2 Testing of the infrastructure work |
The operations which is required to test. |
Checkpoint reporting |
The operations are accurately tested. |
|
Techniques are used to reflect on how testing operations of infrastructure is progressed. |
||||
1.3 Implementation of the storage and computer system |
There is proper implementation of the storage and computer system. |
Highlight reporting |
There is proper implementation of the storage and computer infrastructure. |
|
Highlight reporting is used to reduce the time required to implement the storage and computer system. |
||||
2. Configuration |
2.1 Communication |
Configuration process |
Checkpoint reporting |
Proper communication methods are used to discuss the configuration to complete the project on time. |
Checkpoint reporting is used to check the communication process to progress the configuration items. |
||||
2.2 Hardware |
Hardware system |
Highlight reporting |
The hardware materials are to be configured properly. |
|
Highlight reporting is used to reduce the time needed to implement the virtual desktop infrastructure including hardware system configurations. |
||||
2.3 Software |
Software system |
Highlight reporting |
The software materials are to be configured properly. |
|
Highlight reporting is used to reduce the time needed to implement the virtual desktop infrastructure including software system configurations. |
||||
3. Status Accounts |
3.1 Work packages |
There are gathering of the work package items. |
Checkpoint reporting |
Proper identification of work packages. |
Checkpoint reporting is used to check the progress of the work packages. |
||||
3.2 Planning packages |
There are gathering of the planning packages. |
Highlight reporting |
Proper gathering of the planning packages. |
|
Highlight reporting uses to reduce the time needed to control the plan packages. |
||||
3.3 Accounts planning |
There is proper controlling of the plans. |
Highlight reporting |
Proper controlling of the accounts plan. |
|
Highlight reporting uses to reduce the time needed to control the accounts plan. |
||||
4. Logs |
4.1 Risk register log |
Types of risks |
Highlight reporting |
Risk register, risk management plan is required. |
Highlight reporting uses to reduce the risks which are identified into the risk register. |
||||
4.2 Team management log |
Proper management strategy |
Checkpoint reporting |
Proper managing of the project team |
|
Checkpoint reporting is used to check the progress into the project team members. |
||||
4.3 Monitoring log |
Types of issues |
Highlight reporting |
Monitoring of the issues accurately |
|
It is used to monitor the project related issues and controlled it properly to complete the work on time. |
||||
5. Issues |
5.1 Budget |
Financial risks |
Highlight reporting |
Proper budget plan |
Highlight reporting used to minimize the risks associated with wastage of time into the project budget plan. |
||||
5.2 Lack of communication |
Weekly meetings |
Highlight reporting |
Communication plan |
|
Highlight reporting is used to resolve the issues while in the weekly meetings. |
||||
5.3 Improper training |
Training materials |
Highlight reporting |
Proper training programs |
|
Highlight reporting helps to resolve issues in the training programs for the organizational employees. |
References
Bell, J., 2014. Doing Your Research Project: A guide for first-time researchers. McGraw-Hill Education (UK).
Binder, J., 2016. Global project management: communication, collaboration and management across borders. Routledge.
Chen, X., Li, M. and Damata, L., Microsoft Corp, 2014. Engineering project event-driven social networked collaboration. U.S. Patent 8,707,246.
Demirkesen, S. and Ozorhon, B., 2017. Impact of integration management on construction project management performance. International Journal of Project Management, 35(8), pp.1639-1654.
Fil, O.A., 2015. Project Cost Management. In Materials of the XI International scientific and practical conference,«Trends of modern science» (Vol. 5, p. 92).
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.
Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.
Hornstein, H.A., 2015. The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), pp.291-298.
JOSEPH. PHILLIPS, P.M.P., CBAP, I. and PMP, C., 2018. PMP PROJECT MANAGEMENT PROFESSIONAL STUDY GUIDE. McGraw-Hill Education.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Lei, Z., 2015. Project cost management and project cost control. China Economic Review, 35, pp.232-246.
Lock, D., 2017. The essentials of project management. Routledge.
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology. Taylor & Francis.
Schick, A., 2015. The road to PPB: The stages of budget reform. In Public Budgeting (pp. 39-56). Routledge.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Snyder, C.S., 2014. A guide to the project management body of knowledge: PMBOK (®) guide. Project Management Institute: Newtown Square, PA, USA.
Walker, A., 2015. Project management in construction. John Wiley & Sons.