Project Management in Construction
The management of construction project demands specialized proficiency and knowledge of handling project management tasks. Construction is an area which requires more experience to handle teams of diverse nature to meet the required objectives (“Construction Project Management 101”, 2018). In this technology oriented world effective technologies have paved way for easing the difficulties of construction projects. Similarly, the complexities of construction management are resolved by various helpful methods and tools, such as Microsoft project management and so on. The construction management not just focuses on the tasks to be completed, instead it also gives importance for quality, contract administration and safety management apart from the other basic factors. Further, communication and effectively utilizing the available resources by the defined scope, budget and schedule has a significant role in construction management (Maria Delos Santos, 2017).
Project Management can be defined as an art that effectively directs and helps in coordinating with diverse people and material resources (“Project Management for Construction: Construction Planning”, 2018). However, to help the project managers the Microsoft project software is used widely in the construction field. It has features that help in managing the material resources and human resources effectively (“Project Management for Construction: Labor, Material and Equipment Utilization”, 2018). On the other hand it helps to accomplish the required project on time and helps to have a track of all the tasks to be completed throughout the project (Hendrickson & Au, 2008).
This project aims to provide a clear understanding of the process to be undertaken in the construction of the building. The relative timing to complete the project, relationship between the information flows and the specialist trade packages is also the purpose of this aim.
This project’s objectives are listed below:
- To collect information of the programme.
- To design the IDEF0 process map based on the collected information flow.
- To determine the required time, for the successful completion of the project.
- To assess the effectiveness of Microsoft project software, and
- To determine the critical appraisals related to the implementation of 4D BIM tool, Microsoft project software and ADePT methodology.
This project revolves around the construction of a 50-storey tower i.e., built off of a three-storey podium deck in a city center location. It is basements at two levels. The building’s central core is a concrete construction. It is to be built in front of the floor slabs. The jump form, central tower crane, floor slabs all have a significant role in the construction. The complete construction of the building has reinforced concrete. This is a huge project and required many people to work on designing and on project management. If the design is not understood clearly it can create misunderstandings between the contractors and the managers. The misunderstanding can have negative impact on the management of the work, then on cost and time of the project (“Project Management 101 for Commercial Concrete Polishing Contractors”, 2018).
Specialty Trade Packages in Construction Management
The following are the activities of this project, in a sequence:
- Lifting the screens.
- Reinforcing and column formation.
- Position forming aimed at the band and perimeter beams.
- Beam formation.
- Metal deck positioning.
- Reinforcing and cable stressing process.
- Concrete floor slab execution.
This project’s construction management contains the following specialty trade packages- Core, framework, reinforcement, stressing, concrete, screens and crane. The selected specialty trade package for this project is, “Reinforcement.” The reinforced concrete is a modern material used in construction of buildings. It has the capacity to be molded into the desired shape (“What is reinforcement in construction – Basic Civil Engineering”, 2018).
It is observed that there exists difficulty in clearly understanding process to be undertaken. This is resolved by designing an effective process model for the construction of a 50-storey tower or a building, where the relative timing to complete the project, relationship between the information flows and the specialist trade packages will be determined. Further, this report also aims to determine the advantages and barriers of 4D BIM tool, Microsoft project software and ADePT methodology’s implementation.
For this project, it is recommended to use 4D BIM design tool and ADePT methodology for successfully completing the project on time. On the other hand, this project also ensures to concentrate on the quality, contract administration and safety management along with the other important factors (“Construction Management – Basthatfield”, 2018).
This section of the report emphasizes on the structure of the whole report. The report’s initial section presents the focal point like aim, objectives and background of the study. This section is the introductory part of the whole project.
The second section explores the selected specialist trade package and signifies the purpose and scope in the construction management process. Further, this section is subdivided with the information of IDEF0 process map, for the project. The process mapping is basically a business process model and this model is developed in this part for the selected specialty trade package. The model is designed based on the gathered information as, information flow.
The third section of the report inspects the implementations of Microsoft Project software, 4D BIM tool and ADePT methodology in the construction project. The Microsoft Project software is used for investigating the time constraints, cost and resources required for the project. Gantt chart and the step-by-step tasks required for the project are determined in this specific part. However, Microsoft project is also used to concentrate on its critical appraisal and scrutinizes its competencies to help the project managers, in the construction industry. Additionally, in construction business the advantages and barriers of 4D BIM tool and ADePT methodology’s implementation is determined. This section also includes the critical appraisals for Microsoft Project software.
Microsoft Project Software in Construction Management
The selected specialist trade package is, reinforcement. In construction, reinforcement is held responsible for the structure of the building, thus it is the foundation of the building which has to be monitored effectively. If this goes wrong, then it imposes negative impact on the budget of the project. The following aspects must be taken care (“Concrete and Aggregate Testing”, 2018) (Koutsogiannis, 2018):
- Follow the design (“Construction Project Management | Coursera”, 2018).
- Ensure to check the constructed bar bindings, to manage the risks.
- Follow the guideline for reinforcement (Landau, 2018).
- Ensure right amount of materials are used, with right size, weight and quantity.
- The reinforcement of column, beam and wall has to be carefully monitored by the project manager (“Column Reinforcement”, 2018).
- The bending stress must be cross-checked.
- Tension resistance on the beam must be determined.
- Length of the bar must be checked.
The purpose is to establish an accurate reinforcement to successfully complete the construction of the building. This ensures to secure the building and to fulfill the scope of the project.
This project’s scope is to enhance the construction management with improved techniques and tools, which results in effective co-ordination and cooperation between the workers, project managers and sub-contractors. Further, it ensure the following scopes:
- The problem of lifting the screens will be considered and resolved with effective measures.
- The issues of the processes like, striking and collecting the used materials to pass it to the next above floor will be controlled.
- The necessary security measures will be included, for the safety of the people working on the site.
- The risks will be defined.
- The staff will be trained to follow the newly proposed process.
- The inputs of the project manager, subcontractors and workers will be gathered, to work on improving the process.
- The stressing system will be improved and monitored.
- Improved construction management will be presented.
Coordination between the workers, project managers and sub-contractors are essential in the reinforcement process. Project manager and workers for the following process (“What is reinforcement in construction – Basic Civil Engineering”, 2018) (“Column Reinforcement – Reinforcement Details In Column”, 2018):
- Binding of bars.
- Bar Notation
- Steel bar lapping
- Length of the crank.
- Covering
- Stool in reinforcement.
The reinforcement drawing must be completed and designed correctly, if not it can distort the diameters of the bar and result in wrong reinforcement.
Information supplied by Project manager |
Information supplied by Sub-contractor |
Engineering reports |
Reports of the performed schedule. |
Reports of the schedule. |
Project design |
Requirement of health and safety. |
Cost plan |
Information related to risks at the site. |
Scheduled processes. |
Other construction information |
Safety programme is scheduled |
Inputs of the workers and the sub-contractors. |
Training programme is scheduled |
Cost estimation |
Reports of the performed schedule. |
Schedules of all the processes at the site. |
Inputs of the workers. |
Training programme |
|
Security programme |
For construction of reinforcement, the easily understood process model is provided in this part of the report. The IDEF0 mapping method is utilized to denote the activities and functions of the package (“IDEF0 – Part 1 (understanding it)”, 2018). This model delivers clear understanding of all the necessary processes to be undertaken (Damelio, 2011). The clarity is made possible by the graphical representation of each process in the model (Introduction to IDEF0/3 for Business Process Modelling, 2013). The IDEF0 Process Map is depicted in the below figure.
This section represents the abilities of Microsoft Project software and defines the complete structural construction programme for the selected trade package.
The complete tasks for the construction project are mentioned in the below table.
Task Name |
Construction Floor Cycle Project |
Gathering the Project Requirements |
Analysis the Project Requirements |
Pre-construction of Construction Project |
Prepare project contract Drawings |
Permit Foundation for Project |
Permit full building |
Site utility relocation |
Construction Project Procurement |
Subcontractor bid |
Interview period |
Recommendation of subcontracts |
Approval of subcontracts |
Shoring and sheeting procurement |
Other material procurement |
Construction |
Notice to proceed |
Drill Dewatering Wells |
Install Solider Piles |
Excavation |
Install Lagging |
Install Tiebacks |
Concrete Footings |
Concrete Walls |
Concrete Columns |
Concrete Slab |
Lift screens |
Reinforce and form columns |
Position forms for the band and |
Perimeter beams |
Form beams |
Position metal deck |
Reinforce including stressing |
Cables |
Concrete floor slab |
Inspections & Close?Out |
Weather Day Allowance |
Commissioning & Training |
Final Clean |
Punchlist Generation |
O&M Manual Submission |
Substantial Completion Process |
Substantial Completion |
Resources
Project’s resources are listed below.
Resource Name |
Type |
Initials |
Max. Units |
Std. Rate |
Accrue At |
Base Calendar |
Project Executive |
Work |
P |
100% |
$2,500.00/hr |
Prorated |
Standard |
Work |
S |
100% |
$3,000.00/hr |
Prorated |
Standard |
|
Project Engineer |
Work |
P |
100% |
$2,000.00/hr |
Prorated |
Standard |
Project Admin |
Work |
P |
100% |
$1,900.00/hr |
Prorated |
Standard |
Project Accountant |
Work |
P |
100% |
$1,500.00/hr |
Prorated |
Standard |
Project Scheduler |
Work |
P |
100% |
$1,500.00/hr |
Prorated |
Standard |
Senior Superintendent |
Work |
S |
100% |
$2,000.00/hr |
Prorated |
Standard |
Safety Manager |
Work |
S |
100% |
$1,500.00/hr |
Prorated |
Standard |
Layout Engineer |
Work |
L |
100% |
$1,000.00/hr |
Prorated |
Standard |
Unskilled Laborer |
Work |
U |
100% |
$1,000.00/hr |
Prorated |
Standard |
Equipment and Facilities |
Work |
E |
100% |
$2,500.00/hr |
Prorated |
Standard |
Contractor |
Work |
C |
100% |
$1,000.00/hr |
Prorated |
Standard |
Sub-Contractor |
Work |
S |
100% |
$1,000.00/hr |
Prorated |
Standard |
The overall construction project plan is shown below.
Task Mode |
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Auto Scheduled |
Construction Floor Cycle Project |
266 days |
Fri 3/16/18 |
Fri 3/22/19 |
||
Auto Scheduled |
Gathering the Project Requirements |
1 day |
Fri 3/16/18 |
Fri 3/16/18 |
Project Engineer, Project Scheduler, Senior Project Manager |
|
Auto Scheduled |
Analysis the Project Requirements |
2 days |
Fri 3/16/18 |
Mon 3/19/18 |
Project Engineer, Senior Project Manager |
|
Auto Scheduled |
Pre construction of Construction Project |
10 days |
Fri 3/16/18 |
Thu 3/29/18 |
Layout Engineer, Project Engineer, Senior Project Manager |
|
Auto Scheduled |
Prepare project contract Drawings |
2 days |
Fri 3/30/18 |
Mon 4/2/18 |
4 |
Equipment and Facilities, Layout Engineer, Project Engineer |
Auto Scheduled |
Permit Foundation for Project |
1 day |
Tue 4/3/18 |
Tue 4/3/18 |
5 |
Equipment and Facilities, Senior Project Manager, Senior Superintendent |
Auto Scheduled |
Permit full building |
3 days |
Wed 4/4/18 |
Fri 4/6/18 |
6 |
Equipment and Facilities, Project Engineer, Senior Project Manager |
Auto Scheduled |
Site utility relocation |
5 days |
Mon 4/9/18 |
Fri 4/13/18 |
7 |
Layout Engineer, Senior Project Manager, Senior Superintendent |
Auto Scheduled |
Construction Project Procurement |
14 days |
Mon 4/16/18 |
Thu 5/3/18 |
8 |
|
Auto Scheduled |
Subcontractor bid |
3 days |
Mon 4/16/18 |
Wed 4/18/18 |
Project Engineer, Senior Project Manager, Sub-Contractor |
|
Auto Scheduled |
Interview period |
2 days |
Mon 4/16/18 |
Tue 4/17/18 |
Project Engineer, Senior Project Manager |
|
Auto Scheduled |
Recommendation of subcontracts |
6 days |
Thu 4/19/18 |
Thu 4/26/18 |
10 |
Contractor, Project Admin, Project Executive, Senior Project Manager |
Auto Scheduled |
Approval of subcontracts |
1 day |
Mon 4/16/18 |
Mon 4/16/18 |
Project Engineer[50%],Project Scheduler[50%],Senior Project Manager[50%] |
|
Auto Scheduled |
Shoring and sheeting procurement |
2 days |
Fri 4/27/18 |
Mon 4/30/18 |
12 |
Equipment and Facilities, Layout Engineer, Senior Project Manager, Senior Superintendent |
Auto Scheduled |
Other material procurement |
3 days |
Tue 5/1/18 |
Thu 5/3/18 |
14 |
Project Admin, Project Engineer, Senior Project Manager |
Auto Scheduled |
Construction |
199 days |
Fri 5/4/18 |
Wed 2/6/19 |
9 |
|
Auto Scheduled |
Notice to proceed |
1 day |
Fri 5/4/18 |
Fri 5/4/18 |
Contractor, Equipment and Facilities, Layout Engineer, Senior Project Manager, Senior Superintendent |
|
Auto Scheduled |
Drill Dewatering Wells |
30 days |
Mon 5/7/18 |
Fri 6/15/18 |
17 |
Contractor, Equipment and Facilities, Project Executive, Sub-Contractor, Unskilled Laborer |
Auto Scheduled |
Install Solider Piles |
20 days |
Mon 6/18/18 |
Fri 7/13/18 |
18 |
Contractor, Equipment and Facilities, Project Executive, Sub-Contractor, Unskilled Laborer |
Auto Scheduled |
Excavation |
10 days |
Mon 7/16/18 |
Fri 7/27/18 |
19 |
Equipment and Facilities, Project Executive, Sub-Contractor, Unskilled Laborer |
Auto Scheduled |
Install Lagging |
5 days |
Mon 7/30/18 |
Fri 8/3/18 |
20 |
Equipment and Facilities, Layout Engineer, Project Engineer, Project Executive, Safety Manager |
Auto Scheduled |
Install Tiebacks |
5 days |
Mon 8/6/18 |
Fri 8/10/18 |
21 |
Contractor, Equipment and Facilities, Project Engineer, Project Executive, Unskilled Laborer |
Auto Scheduled |
Concrete Footings |
6 days |
Mon 8/13/18 |
Mon 8/20/18 |
22 |
Equipment and Facilities, Project Engineer, Project Executive, Sub-Contractor, Unskilled Laborer |
Auto Scheduled |
Concrete Walls |
7 days |
Tue 8/21/18 |
Wed 8/29/18 |
23 |
Contractor, Equipment and Facilities, Project Accountant, Project Admin, Project Executive, Unskilled Laborer |
Auto Scheduled |
Concrete Columns |
9 days |
Thu 8/30/18 |
Tue 9/11/18 |
24 |
Contractor, Equipment and Facilities, Project Engineer, Project Executive, Sub-Contractor |
Auto Scheduled |
Concrete Slab |
20 days |
Wed 9/12/18 |
Tue 10/9/18 |
25 |
Contractor, Project Engineer, Project Executive, Sub-Contractor, Unskilled Laborer |
Auto Scheduled |
Lift screens |
12 days |
Wed 10/10/18 |
Thu 10/25/18 |
26 |
Equipment and Facilities, Project Engineer, Project Executive, Sub-Contractor, Unskilled Laborer |
Auto Scheduled |
Reinforce and form columns |
5 days |
Fri 10/26/18 |
Thu 11/1/18 |
27 |
Contractor, Equipment and Facilities, Project Engineer, Sub-Contractor, Unskilled Laborer |
Auto Scheduled |
Position forms for the band and |
7 days |
Fri 11/2/18 |
Mon 11/12/18 |
28 |
Contractor, Equipment and Facilities, Project Engineer, Project Executive, Safety Manager |
Auto Scheduled |
Perimeter beams |
8 days |
Tue 11/13/18 |
Thu 11/22/18 |
29 |
Equipment and Facilities, Project Executive, Sub-Contractor, Unskilled Laborer |
Auto Scheduled |
Form beams |
9 days |
Fri 11/23/18 |
Wed 12/5/18 |
30 |
Project Executive, Project Scheduler, Sub-Contractor |
Auto Scheduled |
Position metal deck |
12 days |
Thu 12/6/18 |
Fri 12/21/18 |
31 |
Equipment and Facilities, Layout Engineer, Project Admin, Sub-Contractor |
Auto Scheduled |
Reinforce including stressing |
8 days |
Mon 12/24/18 |
Wed 1/2/19 |
32 |
Project Engineer, Project Executive, Sub-Contractor |
Auto Scheduled |
Cables |
10 days |
Thu 1/3/19 |
Wed 1/16/19 |
33 |
Equipment and Facilities, Layout Engineer, Project Accountant, Project Engineer |
Auto Scheduled |
Concrete floor slab |
15 days |
Thu 1/17/19 |
Wed 2/6/19 |
34 |
Contractor, Layout Engineer, Project Executive, Project Scheduler, Safety Manager, Sub-Contractor, Unskilled Laborer |
Auto Scheduled |
Inspections & Close?Out |
32 days |
Thu 2/7/19 |
Fri 3/22/19 |
35 |
|
Auto Scheduled |
Weather Day Allowance |
4 days |
Thu 2/7/19 |
Tue 2/12/19 |
10 |
Project Admin, Project Engineer, Project Executive, Project Scheduler, Senior Superintendent |
Auto Scheduled |
Commissioning & Training |
7 days |
Wed 2/13/19 |
Thu 2/21/19 |
37 |
Equipment and Facilities, Project Engineer, Senior Project Manager |
Auto Scheduled |
Final Clean |
9 days |
Fri 2/22/19 |
Wed 3/6/19 |
38 |
Contractor, Equipment and Facilities, Project Admin, Unskilled Laborer |
Auto Scheduled |
Punchlist Generation |
4 days |
Thu 3/7/19 |
Tue 3/12/19 |
39 |
Contractor, Layout Engineer, Project Engineer, Project Executive, Sub-Contractor |
Auto Scheduled |
O&M Manual Submission |
6 days |
Wed 3/13/19 |
Wed 3/20/19 |
40 |
Layout Engineer, Senior Project Manager, Senior Superintendent, Project Admin |
Auto Scheduled |
Substantial Completion Process |
1 day |
Thu 3/21/19 |
Thu 3/21/19 |
41 |
Project Accountant, Project Admin, Senior Project Manager, Senior Superintendent |
Auto Scheduled |
Substantial Completion |
1 day |
Fri 3/22/19 |
Fri 3/22/19 |
42 |
Project Admin, Project Executive, Project Scheduler, Senior Project Manager, Senior Superintendent |
Work Breakdown Structure
Work breakdown structure represented as shown below.
Timing required for the Project Completion
The time required to finish this construction project is 266 days.
Project Cost
The overall project cost is as shown below.
Name |
Actual Cost |
Remaining Cost |
Baseline Cost |
Cost |
Cost Variance |
Construction Floor Cycle Project |
$0.00 |
$16,714,800.00 |
$0.00 |
$16,714,800.00 |
$16,714,800.00 |
The above graph depicts the cost of the whole project.
Cost of the Resources
The total cost of the resources cost are presented in the following table.
Name |
Start |
Finish |
Remaining Work |
Project Executive |
Thu 4/19/18 |
Fri 3/22/19 |
1,488 hrs |
Senior Project Manager |
Fri 3/16/18 |
Fri 3/22/19 |
436 hrs |
Project Engineer |
Fri 3/16/18 |
Tue 3/12/19 |
1,028 hrs |
Project Admin |
Thu 4/19/18 |
Fri 3/22/19 |
392 hrs |
Project Accountant |
Tue 8/21/18 |
Thu 3/21/19 |
144 hrs |
Project Scheduler |
Fri 3/16/18 |
Fri 3/22/19 |
244 hrs |
Senior Superintendent |
Tue 4/3/18 |
Fri 3/22/19 |
168 hrs |
Safety Manager |
Mon 7/30/18 |
Wed 2/6/19 |
216 hrs |
Layout Engineer |
Fri 3/16/18 |
Wed 3/20/19 |
576 hrs |
Unskilled Laborer |
Mon 5/7/18 |
Wed 3/6/19 |
1,176 hrs |
Equipment and Facilities |
Fri 3/30/18 |
Wed 3/6/19 |
1,368 hrs |
Contractor |
Thu 4/19/18 |
Tue 3/12/19 |
1,104 hrs |
Sub-Contractor |
Mon 4/16/18 |
Tue 3/12/19 |
1,368 hrs |
The following are the programme information required for the selected package:
- Schedule for lifting the screens.
- Striking process
- Information of collected used materials.
- Cleaning process
- Stressing system
- Risks
- Scheduled working staff
- Information from the subcontractors and workers, to improve the process.
The highly used software for project management is, “Microsoft Project Software”, because it provides satisfied results. It has smart features to help scheduling. It ensures to work parallel with the tasks and gives effective communication. It tracks the progress and highlights the encountered issues.
The Microsoft project software helps in resolving the following issues.
- Lifting of screens is scheduled based on the available manpower, to avoid any delay of the work.
- The striking process is scheduled.
- Collection of used material is monitored, and the same is sent to the above floor next.
- Cleaning process is scheduled, to avoid any mishaps in the site.
- The stressing system is monitored and scheduled.
- The risks are defined.
- The staff are scheduled to provide the required training, to get accustomed to the newly proposed process.
- The inputs of the project manager, subcontractors and workers have helped in improving the process.
- Improved construction management is presented.
The advantages of implementing the 4D BIM are as follows:
- 4D BIM ensures to benefit the users with four dimensional graphical representation of the building that is designed for construction (Ahmed, Emam & Farrell, 2014).
- It is an effective design tool which helps the development phase of the plans along with its schedule.
- It has significant design features which helps to combine the design and construction.
- It benefits with consistent scheduling and intelligent features.
- It helps to save costs related to rework and scheduling.
The barriers for the effective implementation of the 4D BIM design tool are listed below:
- The construction project managers lack enough skills to work on the 4D BIM tool.
- The users are not provided with sufficient training.
- Availability of the required software and matching the standards of the industry.
- Cost for upgrading the hardware and software at the initial stage can be barrier too (Hardin & McCool, 2015).
The advantages of implementing the ADePT are as follows:
- ADePT is mainly is useful before planning stage (Austin, Baldwin, Li & Waskett, 2000).
- ADePT has better change management handling.
- It seizes any limitations related to building’s drawing (Schultz, 2002).
- ADePT supports to manage the building design, helps in decision making, and in defining the roles.
- It improves project management and helps in prioritizing the work.
The barriers for the effective implementation of the ADePT are listed below:
- Complexity to clearly understand the design.
- Delayed construction.
- Highly expensive
References
Ahmed, S., Emam, H., & Farrell, P. (2014). Barriers to BIM/4D Implementation in Qatar. 1St International Conference On Smart, Sustainable And Healthy Cities [CIB-MENA], At Abu Dhabi, UAE. https://dx.doi.org/10.13140/RG.2.1.4990.4164
Austin, S., Baldwin, A., Li, B., & Waskett, P. (2000). Analytical design planning technique (ADePT): a dependency structure matrix tool to schedule the building design process. Construction Management And Economics, 18(2), 173-182. https://dx.doi.org/10.1080/014461900370807
BIM and the future of AEC. (2018). Autodesk.com. Retrieved 17 March 2018, from https://www.autodesk.com/solutions/bim
Column Reinforcement – Reinforcement Details In Column. (2018). Daily Civil. Retrieved 20 March 2018, from https://www.dailycivil.com/column-reinforcement-details/
Column Reinforcement. (2018). Constructionmanuals.tpub.com. Retrieved 20 March 2018, from https://constructionmanuals.tpub.com/14045/css/Column-Reinforcement-119.htm
Construction Management – Basthatfield. (2018). Basthatfield. Retrieved 19 March 2018, from https://www.basthatfield.com/services/construction-management/
Construction Project Management | Coursera. (2018). Coursera. Retrieved 19 March 2018, from https://www.coursera.org/learn/construction-project-management
Construction Project Management 101. (2018). Smartsheet. Retrieved 20 March 2018, from https://www.smartsheet.com/construction-project-management-101-full
Hardin, B., & McCool, D. (2015). BIM and construction management (2nd ed.).
Hendrickson, C., & Au, T. (2008). Project management for construction. Pittsburgh, Penn.: Carnegie Mellon University.
IDEF0 – Part 1 (understanding it). (2018). Syque.com. Retrieved 19 March 2018, from https://syque.com/quality_tools/tools/Tools19.htm
Introduction to IDEF0/3 for Business Process Modelling. (2013).
Koutsogiannis, A. (2018). Construction Project Management Processes: Everything You Need to Know – GenieBelt. GenieBelt. Retrieved 19 March 2018, from https://geniebelt.com/blog/construction-project-management-processes
Landau, P. (2018). Construction Project Management – A Quick Guide. ProjectManager.com. Retrieved 19 March 2018, from https://www.projectmanager.com/blog/construction-project-management
Maria Delos Santos, J. (2017). What Is Construction Project Management?. project-management.com. Retrieved 20 March 2018, from https://project-management.com/what-is-construction-project-management/
Project Management 101 for Commercial Concrete Polishing Contractors. (2018). For Construction Pros. Retrieved 19 March 2018, from https://www.forconstructionpros.com/business/business-services/article/12281263/project-management-101-for-commercial-concrete-polishing-contractors
Project Management for Construction: Construction Planning. (2018). Cmu.edu. Retrieved 19 March 2018, from https://www.cmu.edu/cee/projects/PMbook/09_Construction_Planning.html
Project Management for Construction: Labor, Material and Equipment Utilization. (2018). Cmu.edu. Retrieved 19 March 2018, from https://www.cmu.edu/cee/projects/PMbook/04_Labor,_Material,_And_Equipment_Utilization.html
Schultz, T. (2002). ADEPT-The Advanced Database Environment for Planning and Tracking. Bell Labs Technical Journal, 3(3), 3-9. https://dx.doi.org/10.1002/bltj.2111
What is reinforcement in construction – Basic Civil Engineering. (2018). Basic Civil Engineering. Retrieved 20 March 2018, from https://www.basiccivilengineering.com/2015/05/what-is-reinforcement-in-construction.htmlA