Time Management Plan
The report is prepared for xyz.com which operates on the ecommerce business for selling different products and service to the users. The organization currently uses an online retail management software for recording some of the business information. The sales order are managed manually and there is a need for the organization to automate the current business process of the organization and reduce the effort of the employees working in the organization. The challenges faced by the organization such as the competitors using more advanced technology for attracting more number of customers and manage all the customer and the product information from a single point. The organization current follows a traditional method for the management of the business process and the employees use manual methodology which can cause error and thus the manual system required to be removed for automation and increasing the efficiency of the organization.
Task Name |
Duration |
Start |
Finish |
Predecessors |
Implementation of e-commerce website for XYZ services company |
107 days |
Thu 05-04-18 |
Fri 31-08-18 |
|
Project planning phase |
15 days |
Thu 05-04-18 |
Wed 25-04-18 |
|
Meeting with project team members |
4 days |
Thu 05-04-18 |
Tue 10-04-18 |
|
Project proposal |
3 days |
Wed 11-04-18 |
Fri 13-04-18 |
2 |
Development of agreement for project |
4 days |
Mon 16-04-18 |
Thu 19-04-18 |
3 |
Identification of the stakeholders for the project |
3 days |
Fri 20-04-18 |
Tue 24-04-18 |
4 |
Project plan approval |
1 day |
Wed 25-04-18 |
Wed 25-04-18 |
5 |
Web Designing |
32 days |
Thu 26-04-18 |
Fri 08-06-18 |
|
Gathering ideas for the design |
5 days |
Thu 26-04-18 |
Wed 02-05-18 |
6 |
Review Client feedback |
4 days |
Thu 03-05-18 |
Tue 08-05-18 |
8 |
Implementation of design revision |
6 days |
Wed 09-05-18 |
Wed 16-05-18 |
9 |
feasibility study on the project |
4 days |
Thu 17-05-18 |
Tue 22-05-18 |
10 |
Estimation of budget for the project |
6 days |
Wed 23-05-18 |
Wed 30-05-18 |
11 |
Arrange meeting for project kick-off |
5 days |
Thu 31-05-18 |
Wed 06-06-18 |
12 |
Final design approval |
2 days |
Thu 07-06-18 |
Fri 08-06-18 |
13 |
Coding |
22 days |
Mon 11-06-18 |
Tue 10-07-18 |
|
Development of the prototype |
4 days |
Mon 11-06-18 |
Thu 14-06-18 |
14 |
Database development |
6 days |
Fri 15-06-18 |
Fri 22-06-18 |
16 |
Code validation |
5 days |
Mon 25-06-18 |
Fri 29-06-18 |
17 |
Cross platform test |
4 days |
Mon 02-07-18 |
Thu 05-07-18 |
18 |
Optimization |
3 days |
Fri 06-07-18 |
Tue 10-07-18 |
19 |
Building of web content |
5 days |
Wed 11-07-18 |
Tue 17-07-18 |
|
Creation of navigation framework |
2 days |
Wed 11-07-18 |
Thu 12-07-18 |
20 |
Development of the content site page |
3 days |
Fri 13-07-18 |
Tue 17-07-18 |
22 |
Development of user experience |
11 days |
Wed 18-07-18 |
Wed 01-08-18 |
|
Documentation of the login details |
3 days |
Wed 18-07-18 |
Fri 20-07-18 |
23 |
Project details update |
4 days |
Mon 23-07-18 |
Thu 26-07-18 |
25 |
Display presentation program |
4 days |
Fri 27-07-18 |
Wed 01-08-18 |
26 |
Analysis of the Project requirement |
12 days |
Thu 02-08-18 |
Fri 17-08-18 |
|
Web application |
4 days |
Thu 02-08-18 |
Tue 07-08-18 |
27 |
Identification of the hardware and the software requirement |
4 days |
Wed 08-08-18 |
Mon 13-08-18 |
29 |
testing and review |
4 days |
Tue 14-08-18 |
Fri 17-08-18 |
30 |
Project closure phase |
10 days |
Mon 20-08-18 |
Fri 31-08-18 |
|
Risk assessment |
4 days |
Mon 20-08-18 |
Thu 23-08-18 |
31 |
Management of the quality |
4 days |
Fri 24-08-18 |
Wed 29-08-18 |
33 |
Final review |
2 days |
Thu 30-08-18 |
Fri 31-08-18 |
34 |
Activity number |
Start date |
Finish date |
Activity name |
Activity description |
Planned action |
Status |
0 |
Thu 05-04-18 |
Fri 31-08-18 |
Implementation of e-commerce website for XYZ services company |
Summary task |
Strategic plan |
Partial |
1 |
Thu 05-04-18 |
Wed 25-04-18 |
Project planning phase |
Starting of the planning phase |
Action plan |
Completed |
1.1 |
Thu 05-04-18 |
Tue 10-04-18 |
Meeting with project team members |
For identification of the requirement |
Action plan |
Completed |
1.2 |
Wed 11-04-18 |
Fri 13-04-18 |
Project proposal |
For approval of the project |
Strategic plan |
Completed |
1.3 |
Mon 16-04-18 |
Thu 19-04-18 |
Development of agreement for project |
For legal purpose |
Strategic plan |
Pending |
1.4 |
Fri 20-04-18 |
Tue 24-04-18 |
Identification of the stakeholders for the project |
For assigning roles and responsibility |
Strategic plan |
Pending |
1.5 |
Wed 25-04-18 |
Wed 25-04-18 |
Project plan approval |
For string the development phase |
Action plan |
Pending |
2 |
Thu 26-04-18 |
Fri 08-06-18 |
Web Designing |
User interactive design |
Action plan |
Pending |
2.1 |
Thu 26-04-18 |
Wed 02-05-18 |
Gathering ideas for the design |
For making it attractive |
Strategic plan |
Pending |
2.2 |
Thu 03-05-18 |
Tue 08-05-18 |
Review Client feedback |
For aligning it to the user needs |
Action plan |
Pending |
2.3 |
Wed 09-05-18 |
Wed 16-05-18 |
Implementation of design revision |
For making the design interactive |
Action Plan |
Pending |
2.4 |
Thu 17-05-18 |
Tue 22-05-18 |
Feasibility study on the project |
For the identification of the risk |
Action Plan |
Pending |
2.5 |
Wed 23-05-18 |
Wed 30-05-18 |
Estimation of budget for the project |
For creation of project funding |
Strategic plan |
Pending |
2.6 |
Thu 31-05-18 |
Wed 06-06-18 |
Arrange meeting for project kick-off |
For informing the stakeholder |
Strategic plan |
Pending |
2.7 |
Thu 07-06-18 |
Fri 08-06-18 |
Final design approval |
Action plan |
Pending |
|
3 |
Mon 11-06-18 |
Tue 10-07-18 |
Coding |
Strategic plan |
Pending |
|
3.1 |
Mon 11-06-18 |
Thu 14-06-18 |
Development of the prototype |
For reducing the error in the final project |
Action plan |
Pending |
3.2 |
Fri 15-06-18 |
Fri 22-06-18 |
Database development |
For storing the product and customer information |
Action plan |
Pending |
3.3 |
Mon 25-06-18 |
Fri 29-06-18 |
Code validation |
Testing the codes |
Action plan |
Pending |
3.4 |
Mon 02-07-18 |
Thu 05-07-18 |
Cross platform test |
For running the website in different devices |
Action plan |
Pending |
3.5 |
Fri 06-07-18 |
Tue 10-07-18 |
Optimization |
For reducing the waiting time |
Action plan |
Pending |
4 |
Wed 11-07-18 |
Tue 17-07-18 |
Building of web content |
Strategic plan |
Pending |
|
4.1 |
Wed 11-07-18 |
Thu 12-07-18 |
Creation of navigation framework |
For connecting the different webpages |
Strategic plan |
Pending |
4.2 |
Fri 13-07-18 |
Tue 17-07-18 |
Development of the content site page |
To guide the user |
Action plan |
Pending |
5 |
Wed 18-07-18 |
Wed 01-08-18 |
Development of user experience |
To attract more number of users |
Action plan |
Pending |
5.1 |
Wed 18-07-18 |
Fri 20-07-18 |
Documentation of the login details |
For administrative purpose |
Action plan |
Pending |
5.2 |
Mon 23-07-18 |
Thu 26-07-18 |
Project details update |
For analyzing the progress of the project |
Action plan |
Pending |
5.3 |
Fri 27-07-18 |
Wed 01-08-18 |
Display presentation program |
For informing the stakeholders |
Action plan |
Pending |
6 |
Thu 02-08-18 |
Fri 17-08-18 |
Analysis of the Project requirement |
For arrangement of the resources |
Strategic plan |
Pending |
6.1 |
Thu 02-08-18 |
Tue 07-08-18 |
Web application |
To interact with the online customers |
Strategic plan |
Pending |
6.2 |
Wed 08-08-18 |
Mon 13-08-18 |
Identification of the hardware and the software requirement |
For deployment of the web server and the database server |
Action plan |
Pending |
6.3 |
Tue 14-08-18 |
Fri 17-08-18 |
Testing and review |
For establishing a secure connection with the user |
Action plan |
Pending |
7 |
Mon 20-08-18 |
Fri 31-08-18 |
Project closure phase |
Action plan |
Pending |
|
7.1 |
Mon 20-08-18 |
Thu 23-08-18 |
Risk assessment |
Identification of the risk |
Strategic plan |
Pending |
7.2 |
Fri 24-08-18 |
Wed 29-08-18 |
Management of the quality |
Reduction of the errors |
Strategic plan |
Pending |
7.3 |
Thu 30-08-18 |
Fri 31-08-18 |
Final review |
Hosting of the website |
Action plan |
Pending |
Utilizing the fact finding the different problems with the current business process is analyzed and the improvement strategy is implemented for meeting the requirements. There are different approaches such as interviews, observation, research and its description is given as follows:
Interviews: It is used for the gap analysis and identification of the organizational strategy used by the business organization to reach the customer.
Questionnaires: It analyzes the requirement of the organization and used as a feedback for the improvement of the current project.
Document review: The It is used for the analysis of the quality and the errors in the project by comparing it with the successful information system available in the market.
Observation: The progress of the project should be observer for identification of the change in the requirement and align it with the current needs of the organization.
Research: Data is collected from different sources for using it in the development of the ecommerce platform for the organization.
From the As Is process diagram it is identified that the sales orders are manually handled and the employee’s needs to manually check the orders for creating a correlation with the business rules of the organization. The employees needs to manually input the customer details and the order details in the information system for the management of the data. The implementation of warehouse automation can resolve the issues and help the organization to maintain a record of their stock.
Creating a strategy for the treatment of the online networking and stick at the arrangement. For processing the orders in the warehouse the orders needs to pass through the warehouse and thus reduce the manual effort of the employees for the management of the details of the orders.
Work Breakdown Structure
After checking the order the information needs to be processed in the information system of the organization. The current business rules of the organization is evaluated for checking the order manually and creation of pick list. The implementation of the automation process would help in reducing the effort of the employees for cross referencing the business information system and maintaining the availability of the product. More information about the product such as product location and details can be maintained with the implementation of the automation process.
- A notification is sent to the warehouse by the employees for the orders that are required to be processed.
- The pick list is used for manually checking the order such as item location and availability of the stocks
- The pick list is printed by the employee and find the product if it is available in the warehouse stock
- If the product is found it is sent for package and shipped to the customer.
The ecommerce market is current growing and the organization faces different types of issues while maintaining the organizational information. For gaining the leading position in the market the organization needs to identify the risk at an early stage and prepare a risk mitigation plan for handling the risk associated with the current business process of the organization. Different encryption algorithm must be used and private clouds should be used for storing the sensitive organizational data from securing the information from external access. The leakage of the information can cause a huge loss for the organization and thus the database needs to be secured from illegal access and secure the customer information for successful deployment of the ecommerce platform.
It is recommended that a sub process of order shipment should be created for shipping the product to the right destination and maintaining a transparency with the customer. The information system should be designed to get all the details of the shipment and store it in the database such that it can be shared with the customer. The sharing of the shipping information helps the customer to track the orders and improve the loyalty of the customer for the business organization.
References
Anbari, F.T., 2018. Innovation, project management, and Six Sigma method. In Current topics in Management (pp. 111-126). Routledge.
Bromiley, P., McShane, M., Nair, A. and Rustambekov, E., 2015. Enterprise risk management: Review, critique, and research directions. Long range planning, 48(4), pp.265-276.
Chaffey, D., 2015. Digital business and E-commerce management. Pearson Education Limited.
Dennis, A., Wixom, B.H. and Tegarden, D., 2015. Systems analysis and design: An object-oriented approach with UML. John wiley & sons.
Gupta, A.K., 2017. Response spectrum method in seismic analysis and design of structures. Routledge.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Laudon, K.C. and Laudon, J.P., 2016. Management information system. Pearson Education India.
Muller, R., 2017. Project governance. Routledge.
Phillips, C.L., Nagle, H.T. and Chakrabortty, A., 2015. Digital Control System Analysis & Design. Pearson Prentice Hall.
Pollack, J. and Adler, D., 2016. Skills that improve profitability: The relationship between project management, IT skills, and small to medium enterprise profitability. International Journal of Project Management, 34(5), pp.831-838.
Pollack, J. and Adler, D., 2016. Skills that improve profitability: The relationship between project management, IT skills, and small to medium enterprise profitability. International Journal of Project Management, 34(5), pp.831-838.
Rainer, R.K., Prince, B. and Watson, H.J., 2014. Management Information Systems. Wiley Publishing.
Valacich, J., George, J. and Hoffer, J., 2014. Essentials of systems analysis and design. Prentice Hall Press.
Yuen, E.C., 2017. The Relationship Between Risk Factors And Profitability of SP Setia Berhad.
Time Management Plan