Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Implementation of Electronic Record Informatics |
261 days |
Mon 08-10-18 |
Mon 07-10-19 |
||
Development of the System |
10 days |
Mon 08-10-18 |
Fri 19-10-18 |
||
Plan Development |
6 days |
Mon 08-10-18 |
Mon 15-10-18 |
Group Leader,Information Manager,Plan Coordinator |
|
Team Selection |
4 days |
Tue 16-10-18 |
Fri 19-10-18 |
3 |
Group Leader,Information Manager,Plan Coordinator |
Team selected |
0 days |
Fri 19-10-18 |
Fri 19-10-18 |
3,4 |
|
Requirement Collection |
39 days |
Mon 08-10-18 |
Thu 29-11-18 |
||
Business Requirement |
7 days |
Mon 22-10-18 |
Tue 30-10-18 |
4 |
Information Manager,Plan Coordinator |
Functional Requirement |
5 days |
Wed 31-10-18 |
Tue 06-11-18 |
7 |
Information Manager,Plan Coordinator |
Non-Functional Requirement |
3 days |
Wed 31-10-18 |
Fri 02-11-18 |
7 |
Information Manager,Plan Coordinator |
Summarising Requirement |
5 days |
Wed 07-11-18 |
Tue 13-11-18 |
7,8,9 |
Information Manager,Plan Coordinator |
List of key Requirements |
5 days |
Wed 14-11-18 |
Tue 20-11-18 |
10 |
Information Manager,Plan Coordinator |
Strategy Development |
7 days |
Wed 21-11-18 |
Thu 29-11-18 |
11 |
Group Leader,Information Manager,Plan Coordinator |
Requirement Collection Completed |
0 days |
Mon 08-10-18 |
Mon 08-10-18 |
10,11 |
|
Development Phase |
10 days |
Wed 21-11-18 |
Tue 04-12-18 |
||
Programming |
10 days |
Wed 21-11-18 |
Tue 04-12-18 |
11 |
Information Manager |
UI designing |
6 days |
Wed 21-11-18 |
Wed 28-11-18 |
11 |
Information Manager |
System Development Completed |
0 days |
Tue 04-12-18 |
Tue 04-12-18 |
15,16 |
|
Testing |
17 days |
Wed 05-12-18 |
Thu 27-12-18 |
||
Testing |
10 days |
Wed 05-12-18 |
Tue 18-12-18 |
14,15 |
Information Manager |
Making Necessary Changes |
6 days |
Wed 19-12-18 |
Wed 26-12-18 |
19 |
Information Manager |
Submission |
1 day |
Thu 27-12-18 |
Thu 27-12-18 |
20 |
Group Leader |
Testing Successful |
0 days |
Wed 26-12-18 |
Wed 26-12-18 |
19,20 |
|
Implementation Team |
10 days |
Wed 05-12-18 |
Tue 18-12-18 |
||
Identifying Skill need |
5 days |
Wed 05-12-18 |
Tue 11-12-18 |
14 |
Group Leader, Information Manager |
Selecting Suitable Candidate by Skill Testing |
3 days |
Wed 12-12-18 |
Fri 14-12-18 |
24 |
Group Leader, Information Manager |
Agreement Sign Off |
2 days |
Mon 17-12-18 |
Tue 18-12-18 |
25 |
Group Leader, Plan Coordinator |
Milestone 1: Phase Completed |
0 days |
Tue 18-12-18 |
Tue 18-12-18 |
26 |
|
Configuration of Software |
20 days |
Wed 19-12-18 |
Tue 15-01-19 |
23 |
|
Software identification to support the System |
4 days |
Wed 19-12-18 |
Mon 24-12-18 |
Information Manager, Plan Coordinator |
|
Security Assessment |
10 days |
Tue 25-12-18 |
Mon 07-01-19 |
29 |
Information Manager |
Development of a build element list |
10 days |
Tue 25-12-18 |
Mon 07-01-19 |
29 |
Information Manager |
Configuring software |
6 days |
Tue 08-01-19 |
Tue 15-01-19 |
30,31 |
Information Manager |
Milestone 2: Phase Completed |
0 days |
Tue 15-01-19 |
Tue 15-01-19 |
32 |
|
Identification of Hardware Phase |
23 days |
Wed 16-01-19 |
Fri 15-02-19 |
28 |
|
Identify Structure |
6 days |
Wed 16-01-19 |
Wed 23-01-19 |
Information Manager, Plan Coordinator |
|
Identifying Hardware Need |
10 days |
Thu 24-01-19 |
Wed 06-02-19 |
35 |
Information Manager, Plan Coordinator |
Configure Hardware |
17 days |
Thu 24-01-19 |
Fri 15-02-19 |
35 |
Information Manager |
Milestone 3:Phase Completed |
0 days |
Fri 15-02-19 |
Fri 15-02-19 |
37 |
|
Data Transfer |
60 days |
Mon 18-02-19 |
Fri 10-05-19 |
34 |
|
Determine approach |
2 days |
Mon 18-02-19 |
Tue 19-02-19 |
Group Leader, Information Manager |
|
Sort and Filter Data |
40 days |
Wed 20-02-19 |
Tue 16-04-19 |
40 |
Information Manager, Plan Coordinator |
Develop Checklist |
2 days |
Wed 17-04-19 |
Thu 18-04-19 |
41 |
Group Leader, Information Manager, Plan Coordinator |
Migrate Data |
12 days |
Wed 17-04-19 |
Thu 02-05-19 |
41 |
Information Manager |
Check Data Status |
6 days |
Fri 03-05-19 |
Fri 10-05-19 |
43 |
Plan Coordinator |
Milestone 4: Phase Completed |
0 days |
Fri 10-05-19 |
Fri 10-05-19 |
44 |
|
Optimisation of Pre-Launch Workflows |
31 days |
Mon 13-05-19 |
Mon 24-06-19 |
39 |
|
Identify Feasibility |
16 days |
Mon 13-05-19 |
Mon 03-06-19 |
45,38,33,27 |
Group Leader, Information Manager |
Check Success of previous steps |
15 days |
Tue 04-06-19 |
Mon 24-06-19 |
47 |
Information Manager, Plan Coordinator |
Milestone 5: Phase Completed |
0 days |
Mon 03-06-19 |
Mon 03-06-19 |
47 |
|
Launch Approach |
20 days |
Tue 25-06-19 |
Mon 22-07-19 |
46 |
|
Consider Layout |
10 days |
Tue 25-06-19 |
Mon 08-07-19 |
Group Leader |
|
Consider Business requirement |
5 days |
Tue 09-07-19 |
Mon 15-07-19 |
51 |
Group Leader |
Decide on Approach |
5 days |
Tue 16-07-19 |
Mon 22-07-19 |
52 |
Group Leader, Information Manager |
Milestone 6: Phase Completed |
0 days |
Mon 22-07-19 |
Mon 22-07-19 |
53 |
|
Policies Defining |
25 days |
Tue 23-07-19 |
Mon 26-08-19 |
50 |
|
Consider Business requirement |
4 days |
Tue 23-07-19 |
Fri 26-07-19 |
Group Leader, Information Manager |
|
Consider Legal and Ethical aspects |
8 days |
Mon 29-07-19 |
Wed 07-08-19 |
56 |
Group Leader, Information Manager |
Develop Policy |
13 days |
Thu 08-08-19 |
Mon 26-08-19 |
57 |
Group Leader, Information Manager, Plan Coordinator |
Milestone 7: Phase Completed |
0 days |
Mon 26-08-19 |
Mon 26-08-19 |
58 |
|
Training Plan |
26 days |
Tue 27-08-19 |
Tue 01-10-19 |
55 |
|
Assess Stakeholders |
10 days |
Tue 27-08-19 |
Mon 09-09-19 |
Group Leader, Information Manager |
|
Measure system Complexity |
5 days |
Tue 10-09-19 |
Mon 16-09-19 |
61 |
Information Manager |
Determine Training approach |
5 days |
Tue 10-09-19 |
Mon 16-09-19 |
61 |
Information Manager, Plan Coordinator |
Consult with high Officials |
2 days |
Tue 17-09-19 |
Wed 18-09-19 |
63 |
Group Leader |
Develop training Plan |
9 days |
Thu 19-09-19 |
Tue 01-10-19 |
61,62,63,64 |
Information Manager, Plan Coordinator |
Milestone 8: Phase Completed |
0 days |
Tue 01-10-19 |
Tue 01-10-19 |
65 |
|
Implementation |
4 days |
Wed 02-10-19 |
Mon 07-10-19 |
46,50,39 |
|
Present plan |
1 day |
Wed 02-10-19 |
Wed 02-10-19 |
65 |
Group Leader |
Implementation |
3 days |
Thu 03-10-19 |
Mon 07-10-19 |
68 |