Client’s Introduction and Project Background
The paper is based on development of “La Cafe Android Application” which is used for pre-requesting breakfast and also unique sorts of refreshments. La Café utilizes android application keeping in mind the end goal to make an application that will be introduced in close-by computerized payment framework so that the clients can pay their bill before gathering their requests from the La Café counter. This innovation is particularly profitable for the client who requires to be served helpfully and also rapidly. The framework is additionally useful in catching more number of clients which additionally helps with expanding the whole income of the association. The paper explains the foundation of the project, client’s necessity, and partner’s investigation and in addition project objectives. The paper likewise audits a few literary works keeping in mind the end goal to outline proper technique, apparatuses and guidelines for the project.
The La Café builds up the android application as it confronts number of difficulties in gathering the cash from the clients. The clients likewise need to remain in line keeping in mind the end goal to pay their bill. The administration that is given by the cafe is not helpful and speedy. The associations likewise need to utilize staffs with a specific end goal to deal with the payment framework and the whole technique of charging and payment is tedious which disappoints the clients.
Keeping in mind the end goal to determine this whole issue the association “La Café” builds up an android application that is useful for facilitating different sorts of refreshments and breakfast. The application that is created can be introduced in any of the close-by Automated Payment System so that the clients can pay before they devour the nourishment (Cicmil et al., 2017). The advancement of the application helps the clients as well as the association. The clients who need advantageous and also snappy administration can utilize this application for booking their requests and can pay effortlessly with the assistance of the application. Then again, the application is useful in drawing in more number of clients which helps with upgrading the whole income of the association. In this way the advancement of android application inside the La Café helps in settling every one of the issues that the association is for the most part confronting because of manual operation inside the association.
The association “La Café” builds up an android application with a specific end goal to meet every one of the prerequisites of the clients suitably. The client of the la Café needs helpful and brisk administration from the association. With the assistance of the android application the clients can without much of a stretch enlist to the administration of the Café house by entering a portion of the particular subtle elements. In the wake of enrolling they can go into their record at whatever point they need. This element helps the clients to arrange diverse sorts of refreshments and additionally breakfast (Hill, 2013). The principle menus have distinctive options that the clients’ needs, for example, kind of espresso, amount, size and that’s just the beginning. This procedure in finished with the assistance of the application which helps in making the procedure advantageous as well as aides in diminishing the whole time required which is considered as one of the vital need of the clients.
Detailed Analysis of Client’s Requirements
The clients need to choose their menus within the sight of number of decisions. The android application helps in giving the decisions so that the clients can choose drinks or breakfast according to their need. It is dissected that the clients are not glad in the event that they need to remain in line for a considerable length of time keeping in mind the end goal to pay the bill. In this manner the clients dependably needs simple and less tedious technique so they don’t need to invest much energy in paying the bill (Heagney, 2016). The android application that is produced by the La Café can be introduced inside any of the close-by mechanized payment framework and with the assistance of that the clients can pay their bill effectively in a less time before they devour the sustenance. It is recognized that the android application is useful in focusing on more number of clients particularly in the morning which helps in mirroring that the framework is useful in addressing the necessities and prerequisites of the clients fittingly (Kasemsap, 2016). The framework is produced such that it can record the data of the clients which help the association to give decisions on make those refreshments that suit the way of life of the clients. The application additionally fuses combination through which the clients can give criticism and in addition audits which will be useful in empowering different sorts of restorative measures and also client’s faithfulness.
Role |
Responsibilities |
Project Sponsor |
The sponsor of the project is the individual who is dependable of favoring the project. The project support helps in giving money related support to the project. They usually work with the administration group of the project particularly with the matters that incorporate subsidizing, illumination, observing and more. The project is driven by the project support by making appropriate choice and also engagement method that is approved formally and in this manner it helps in assuming an essential part in the advancement of project extension and additionally sanction. |
Project Manager |
Project manager is the individual who is dependable of dealing with the whole project in setting to time, spending plan, and scope and in addition quality keeping in mind the end goal to convey legitimate and additionally fitting expectations that aides in fulfilling the clients. The project supervisor additionally includes in project start, arranging, outline, checking and also execution for actualizing the whole project effectively inside the assessed spending plan and in addition time. The project chief additionally includes in investigating different sorts of dangers which are related with the project keeping in mind the end goal to determine and additionally relieve them suitably. They likewise get legitimate guidance from the direction and from fitting specialized expert with the goal that they can assess the contentions according to the provisos of the agreement. |
Contracting Legal officer |
Contracting lawful officer is the individual who has the specialist to end or change a concession to the eatery benefit. This is the individual who by and large intercedes in any of the understanding by including with the outsider and in addition with the cafe eatery. They for the most part includes in recognizing and in addition assessing the associations irreconcilable situations effectively in the obtaining method. |
Contractors |
Contractors are the people who have a place with various foundations or association and they are mindful of giving legitimate data and also guidance on the framework advancement. The people incorporate specialists, programming examiner, professionals and mentors. The people help in giving fitting data or counsel so that the application can be effectively created for meeting every one of the destinations and additionally objectives of the Café eatery. |
Employees of café |
The employees of the cafe are the people who are capable of dealing with all the specialized parts of the framework including breaking down necessities and also prerequisites of the framework, its plan, usage and that’s just the beginning. The specialized workers for the most part help in offering legitimate specialized administration and in addition companies to the association so that all the specialized parts of the framework can be kept up appropriately keeping in mind the end goal to give legitimate operation of the framework. |
IT technical employee |
IT specialized representatives are the general population who are capable of overseeing and also keeping up the security of data innovation that is used with the application so as to give appropriate approval and in addition validation to different information and data of the customer. The IT specialized staffs for the most part work in conference with the representatives of the bistro keeping in mind the end goal to give legitimate security and in addition upkeep to the data arrangement of the association. |
The principle objective of the project is to build up an android application that will be useful in pre-requesting different sorts of refreshments and breakfast. The reasonable pre-requesting framework that will be created is introduced in any of the close-by computerized payment framework so that the clients can pay effortlessly before they expend the nourishment. The association needs to give such pre-requesting administration that it will be useful in focusing on expansive number of clients which will promote accommodating in raising the whole income of the association (Marcelino-Sádaba et al., 2014). The framework is produced so that the clients can pick their requests rapidly and in addition advantageously from the counter of the bistro. The framework is composed fittingly so it can record all the data of the clients while they enlist with their contact points of interest. This aides in offering the sorts of refreshments that matches with necessities and also way of life of the clients. The association likewise goes for coordinating a criticism framework so that the clients can give suggestion, surveys and also input which will be useful in empowering different sorts of restorative measures and also client’s faithfulness.
Stakeholder Analysis
As indicated by Schwalbe (2015), project approach is characterized as the cycle that aides in characterizing, arranging, propelling, overseeing and in addition shutting different periods of the project. Every particular project stage helps in tending to a specific angle for dealing with the project. It is broke down that there are fundamentally five sorts of project systems that can be pertinent in the project. The philosophies incorporate Waterfall project administration, lithe project administration, basic chain, Prism and PRINCE2.
It is expressed by Kerzner (2013), that waterfall system helps in overseeing different exercises of project successively which incorporates start stage, arranging stage, improvement stage, quality affirmation stage lastly the project fulfillment stage. The different prerequisites of the project are shown at the beginning period of the project with particularly little change to the whole arrangement of the project until it is required fundamentally. The system is by and large used for different sorts of vast scale programming improvement with the assistance of legitimate arranging and proper unsurprising method and in addition vital.
Then again, it is opined by Turner (2014), that spry methodology by and large concentrates on versatility for evolving circumstances, standard criticisms and that’s just the beginning. It is used whether the likelihood of circumstance changing is high either from the customers end or from the association’s end. This methodology is by and large required when the clients or the administration of the association should be on the creation system that outcomes in different sorts of changing prerequisites and also exceptional poops in the assignments of the group. Spry procedure is by and large used for the product projects whose primary goal is to give speedy and in addition viable administrations to the clients. The strategy helps in supporting different sorts of proceeding with advancement of various programming improvement strategies (Martinelli & Milosevic 2016). The advantage that the project accomplishes by using light-footed approach incorporate straightforwardness, unsurprising conveyance, unsurprising expense and additionally plan, permit change, help in concentrating on business esteem and furthermore helps with enhancing quality.
The Project methodology that is viewed as proper for this project is lithe strategy. This is on the grounds that the nimble procedure helps in giving snappy and constant conveyance of items to its clients. It is proposed by the specialists that spry technique helps in giving one of a kind chances to the clients for including in the project. The strategy is useful in conveying much of the time and in addition advantageously to enhance the business estimation of the association (Braglia & Frosolini 2014). At the point when the colleagues are particularly centered on conveyance then an open door is available to refine and in addition reprioritize the general accumulation in the framework. It is additionally considered as a standout amongst the best apparatus for programming improvement and it encourages in giving advantages to both the clients and in addition to the association.
It is broken down that for this project, the project administration instrument that can be utilized is Gantt diagram. Gantt outline is particularly straightforward and in addition costly and it helps in mirroring the exercises that will be performed for finishing the whole project effectively. The Gantt diagram helps in showing the circumstances and in addition assets that are required for finishing each undertaking. On the off chance that the project supervisor can finish the whole project according to the assessed spending plan and time then the project is thought to be effective (Too & Weaver, 2014). It is examined that the Gantt outline helps in giving legitimate data about the exercises that are important to lead with a specific end goal to build up the android application properly.
As indicated by McNeil, Frey and Embrechts (2015), waterfall and in addition dexterous project system concentrates more on timetables and calendars while the basic chain method is equipped more towards settling challenges that are related with project assets. Each project has a particular course of action of focus segments, called basic tie that development a project base timetable. The basic chain methodology gives adequate advantages for this basic chain while submitting enough resources for various endeavors to such a degree, to the point that they can run at the same time, yet in the meantime to reassign assets when required. This setup is ideal for resource overpowering gatherings, or for the people who have adaptability in the expertise set of the colleagues. It is satisfied by Pritchard and PMP (2014), the approach of Prism is by and large created by GPM Global keeping in mind the end goal to build up a philosophy that takes different sorts of ecological variables while building up an effective and also legitimate technique that can be appropriately incorporated with huge tasks. It is viewed as one of the remarkable strategies that need accreditation from the project directors. This philosophy is for the most part reasonable for land improvement project that may have antagonistic effect on the earth.
Then again, it is contended by Burke (2013), PRINCE2 is one of the systems that is embraced by the administration and was discharged and also upheld by the legislature of UK in the year 1996. It is considered as one of the technique situated strategy that aides in partitioning projects into number of stages each with various plans and additionally methodology, PRINCE2 is considered as confused technique yet the project chiefs are mindful to decide if the tasks can be scale legitimately with a portion of the particular prerequisites.
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
0 |
La café Android application development |
133 days |
Wed 3/15/17 |
Fri 9/15/17 |
|
1 |
Project proposal development |
45 days |
Wed 3/15/17 |
Tue 5/16/17 |
|
2 |
Completed infrastructure |
30 days |
Wed 5/17/17 |
Tue 6/27/17 |
1 |
3 |
Prototype testing |
25 days |
Wed 6/28/17 |
Tue 8/1/17 |
2 |
4 |
Capacity trainings & implementation |
20 days |
Wed 8/2/17 |
Tue 8/29/17 |
3 |
5 |
Project closure |
13 days |
Wed 8/30/17 |
Fri 9/15/17 |
4 |
There are number of project administration apparatuses that can be used in the project. The viable project administration devices incorporate Gantt diagram, rationale arrange, PERT graph, item breakdown structure and in addition work breakdown structure. As indicated by Svejvig and Andersen (2015), Gantt graph is especially straightforward and additionally costly and it helps in mirroring the exercises that will be performed for finishing the whole project effectively. The Gantt graph helps in showing the circumstances and assets that are required for finishing each undertaking. It is examined that the Gantt outline helps in giving legitimate data about the exercises that are important to direct so as to build up the android application properly.
Then again, it is contended by Turner (2016), that rationale organize for the most part aides in demonstrating different groupings of exercises in a project after some time. It helps in mirroring the different project exercises intelligently. It is used for recognizing different turning points and basic way of the project. It likewise helps in giving appropriate comprehension about the conditions of the project, its timescale and additionally work process. It is investigated by Mir and Pinnington (2014), that program assessment and survey system is one of the models of project administration that can be created in the United States in the year 1958. It is one of the techniques that are utilized for breaking down various sorts of errands that is by and large used for finishing a given project, time required for finishing each undertaking and recognizable proof of least time that is required to finish the whole project.
It is opined by Fleming and Koppelman (2016), that Product Breakdown Structure (PBS) is characterized as a far reaching, different leveled tree structure of parts that aides in making appropriate project deliverable which are composed legitimately in the whole project. A PBS can be useful in clarifying expectations of the project and furthermore helps to manufacture a work breakdown structure. The PRINCE2 project administration strategy prescribes the usage of thing based orchestrating, some bit of which is working up a Product Breakdown Structure.
Then again, it is opined by Lientz and Rea (2016), a Work Breakdown Structure is characterized as a progressive decay of the different expectations that are required for finishing the whole project. It likewise helps hotel separating the different expectations into reasonable work bundles which can be planned and appointed legitimately to the project. Work breakdown structure is considered as one of the standard administration device that is essentially used for legitimate planning for project.
References
Braglia, M., & Frosolini, M. (2014). An integrated approach to implement project management information systems within the projected enterprise. International Journal of Project Management, 32(1), 18-29.
Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.
Cicmil, S., Cooke-Davies, T., Crawford, L., & Richardson, K. (2017, April). Exploring the complexity of projects: Implications of complexity theory for project management practice. Project Management Institute.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt Assn.
Hill, G. M. (2013). The complete project management office handbook. CRC Press.
Kasemsap, K. (2016). The roles of information technology and knowledge management in project management metrics. Project Management: Concepts, Methodologies, Tools, and Applications: Concepts, Methodologies, Tools, and Applications, 229.
Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Lientz, B. & Rea, K. (2016). Breakthrough technology project management. Routledge.
Lock, M. D. (2014). The essentials of project management. Ashgate Publishing, Ltd..
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., & Villanueva, P. (2014). Project risk management methodology for small firms. International Journal of Project Management, 32(2), 327-340.
Martinelli, R. J., & Milosevic, D. Z. (2016). Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
McNeil, A. J., Frey, R., & Embrechts, P. (2015). Quantitative risk management: Concepts, techniques and tools. Princeton university press.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International Journal of Project Management, 32(2), 202-217.
Newton, R. (2016). Project management step by step: how to plan and manage a highly successful project. Pearson UK.
Pritchard, C. L., & PMP, P. R. (2014). Risk management: concepts and guidance. CRC Press.
Reiss, G. (2013). Project management demystified: Today’s tools and techniques. Routledge.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), 278-290.
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), 1382-1394.
Turner, J. R. (2014). The handbook of project-based management (Vol. 92). New York, NY: McGraw-hill.
Turner, R. (2016). Gower handbook of project management. Routledge.