Time Management Plan
GoCatch is the organization that has been selected and it is a company that provides taxi and rideshare services to the people of Australia. The organization is locally owned and has been expanding rapidly due to the demand of transportation services from the customers. The primary users that are associated with GoCatch since its inception in 2010 are the drivers and the passengers. The company makes use of a web based application for booking of taxi services.
Activity Number |
Start |
Finish |
Task Name |
Description |
Status |
1 |
Mon 6/12/17 |
Wed 12/13/17 |
GoCatch |
||
2 |
Mon 6/12/17 |
Mon 6/26/17 |
Project Start-up |
||
3 |
Mon 6/12/17 |
Thu 6/15/17 |
Technical Feasibility |
Determination of feasibility on technical grounds |
Not yet started |
4 |
Fri 6/16/17 |
Tue 6/20/17 |
Result study and analysis |
Understanding of the results |
Not yet started |
5 |
Wed 6/21/17 |
Fri 6/23/17 |
Chartering tasks and processes |
Inclusion of the results in the charter document |
Not yet started |
6 |
Mon 6/26/17 |
Mon 6/26/17 |
Milestone One: Project Charter |
Not yet started |
|
7 |
Mon 6/26/17 |
Mon 7/31/17 |
Planning Phase |
Not yet started |
|
8 |
Tue 6/27/17 |
Tue 7/4/17 |
Scope determination |
Finalization of the items to be covered and the ones not to be covered |
Not yet started |
9 |
Wed 7/5/17 |
Fri 7/7/17 |
Risk and Threat Analysis |
Determination of the risks and the strategy to be taken |
Not yet started |
10 |
Mon 7/10/17 |
Wed 7/12/17 |
Design and finalization of budget |
Creation of the budget for the project |
Not yet started |
11 |
Thu 7/13/17 |
Mon 7/17/17 |
Design and finalization of schedule |
Creation of the schedule for the project |
Not yet started |
12 |
Tue 7/18/17 |
Fri 7/21/17 |
Selection of communication methodology |
Communication mechanisms and methodologies |
Not yet started |
13 |
Mon 7/24/17 |
Fri 7/28/17 |
Team allocation |
Selection of project resources and assignment of duties |
Not yet started |
14 |
Mon 7/31/17 |
Mon 7/31/17 |
Milestone Two: Project Plan |
Not yet started |
|
15 |
Mon 7/31/17 |
Thu 10/5/17 |
Project Execution |
Not yet started |
|
16 |
Tue 8/1/17 |
Tue 8/8/17 |
Procurement processes |
Obtaining of the tools and required equipment |
Not yet started |
17 |
Wed 8/9/17 |
Wed 8/16/17 |
Application design and UI aspects |
Design of the application and its UI aspects |
Not yet started |
18 |
Thu 8/17/17 |
Mon 8/21/17 |
Wireframes and review |
Review of design and submission of wireframes |
Not yet started |
19 |
Tue 8/22/17 |
Mon 9/25/17 |
Source code creation |
Coding process |
Not yet started |
20 |
Tue 9/26/17 |
Wed 10/4/17 |
Sync with database |
Integration of front end with back end |
Not yet started |
21 |
Thu 10/5/17 |
Thu 10/5/17 |
Milestone 3: Source Code |
Not yet started |
|
22 |
Thu 10/5/17 |
Fri 11/24/17 |
Project Control |
Not yet started |
|
23 |
Fri 10/6/17 |
Mon 10/16/17 |
Implementation on cloud |
To be done on a private cloud |
Not yet started |
24 |
Tue 10/17/17 |
Wed 10/25/17 |
Management of changes |
Preparation, execution and reinforcement of changes |
Not yet started |
25 |
Thu 10/26/17 |
Fri 11/3/17 |
Testing and integration |
System and UI testing and integration with rest of the modules |
Not yet started |
26 |
Mon 11/6/17 |
Tue 11/14/17 |
Inspection cycles |
Evaluation processes |
Not yet started |
27 |
Wed 11/15/17 |
Thu 11/23/17 |
Performance measurement |
Measurement of performance of the resources |
Not yet started |
28 |
Fri 11/24/17 |
Fri 11/24/17 |
Milestone 4: Defect Report |
Not yet started |
|
29 |
Fri 11/24/17 |
Wed 12/13/17 |
Project Closure |
Not yet started |
|
30 |
Mon 11/27/17 |
Wed 12/6/17 |
Lessons learned |
Documentation in the form of a report |
Not yet started |
31 |
Thu 12/7/17 |
Fri 12/8/17 |
Acceptance and system documentation |
Sign offs and discussions with the stakeholders on deliverables |
Not yet started |
32 |
Mon 12/11/17 |
Tue 12/12/17 |
Final report |
Preparation of the completion report of the project |
Not yet started |
33 |
Wed 12/13/17 |
Wed 12/13/17 |
Milestone 5: Closure Report |
Not yet started |
The AS-IS diagram that has been designed for GoCatch includes the mechanisms of booking of the taxi and cabs online with mechanisms such as availability check, response, pickup, drop etc included in the diagram. The To-Be diagram for the application includes addition of tools such as CRM tools so that the customer may share and seek feedback of the drivers and ensure that the services provided do not compromise on the quality. There is also a tracking tool that has been included in the to-be diagram that will allow the passenger to share ride details with friends and family which may be tracked from the security point of view (Patrick, 2015). Also, the process has been changed wherein when a customer drops a request for cab, it will be sent to all the drivers. The customer then chooses the nearest confirmed drivers. Then the system asks for payment type. Once customer makes the payment, booking is confirmed.
The application shall make use of tree topology in terms of the physical network topology as it will provide many access points to be present. In this manner, there will not be a single point that may lead to failure of the entire application.
Mesh topology shall be used as the logical network topology in this case as it will provide a string knitted architecture with connections and enhanced connectivity between the nodes.
Testing Type |
Description of testing Activity |
Test Data |
Functional Testing |
This testing type shall include the testing of the functional aspects of the application. There will be many functionalities that the application will have for the passengers and the drivers which shall be validated in terms of correctness and accuracy |
Test data used will be the dummy data that will have a close similarity with the real data. |
Regression Testing |
The development cycles will improve on the application as every new build that will be provided will correct the defects detected in previous build. This testing process will validate the bugs and defects from the previous build for their correctness and impact on the other sections of the application. |
Test data used will be the dummy data that will have a close similarity with the real data. |
Cloud Testing |
It will include the testing of the implementation status and accuracy on the cloud and integration with rest of the systems |
Test data used will be the dummy data that will have a close similarity with the real data. |
Load Testing |
The testing process will aim to check the performance of the application by increasing the load in terms of number of users etc. |
Test data used will be the dummy data that will have a close similarity with the real data. |
UI Testing |
UI aspects of the application will be validated |
Test data used will be the dummy data that will have a close similarity with the real data. |
User Acceptance Testing |
A build will be released for a section of end users for their feedback and response to the application. |
Real data that is the production data will be utilized |
The testing activities will ensure that the application that is developed for GoCatch is validated from the perspective of every type of user.
- CEO and Directors: Training activities will include the conduction of sessions on critical application areas, its utility, query areas and the benefits that the application will provide to GoCatch.
- Managers and Analysts: Utility of the application to generate maximum profits and good customer experience will be the prime focus of the training activities that will be provided to this group of users.
- Technical and Operational Staff Members: Details of the execution of the features, the security risks that may occur due to an error and steps to prevent such an occurrence will be the tasks that will be covered in trainings
- Support and Maintenance Staff: Incident recording and response will be explained to the users along with the major query areas and frequently asked questions regarding the application (Rose, 2014).
Changeover and migration from the existing system to the new system that is developed for GoCatch shall be done by following the induction and completion of various steps (Majedran, 2013).
There shall be analysis that shall be done and a listing of the changes and the modification to be implemented shall be made followed by creation of a plan to do so. The changeover shall be initiated thereafter in which the migration and conversion shall begin and the same shall be regularly monitored and inspected in terms of status and progress.
- GoCatch application shall provide the passengers and the drivers with the ability to easily acquire the services provided by the organization in terms of bookings, cancellations, availability checks, feedbacks, pick and drop and maintenance of history.
- Project tasks and activities must reflect ethical practices and quality standards implemented.
- Design and development of the application for GoCatch
- Syncing of the front end with the database at the back end
- Implementation of the application on a private cloud
- System, UI and performance testing and integration
- System documentation for the application
The project for the creation and deployment of the application for GoCatch shall take place through a well defined process. The process shall include a series of steps in which the steps such as startup, planning, design & development, monitoring & control and closure shall be present (Kumar, 2012).
The processes that will be included in the successful completion of the project will be backed by a planning and analysis of all the aspects so that there are no errors and mistakes that may occur in terms of planning activities. Monitoring and management will also be carried out.
Conclusion
GoCatch is an organization that is present in the business since last seven years. It is required that the organization improvises on the offerings by enhancing its information system and the same has been explained in the report with the use of the online application for booking of the rides. The passengers and drivers will be the users of the application and it shall be ensured that the application is secure and there are protection mechanisms built in the application.
References
Kumar, S. (2012). Cloud computing- Research issues, challenges, architecture, platforms, and application: A survey. 1st ed. [ebook] Available at: https://www.ijfcc.org/papers/95-F0048.pdf [Accessed 30 May 2017].
Majedran, S. (2013). Organizational challenges in cloud adoption and enablers of cloud transition program. 1st ed. [ebook] Available at: https://web.mit.edu/smadnick/www/wp/2013-13.pdf [Accessed 30 May 2017].
Patrick, L. (2015). Why is As Is business process analysis is appropriate. 1st ed. [ebook] Available at: https://www.bridging-the-gap.com/as-is-business-process/ [Accessed 30 May 2017].
Rose, G. (2014). Information technology and organizational learning. 1st ed. [ebook] Available at: https://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.114.6&rep=rep1&type=pdf [Accessed 30 May 2017].