WBS |
Task Name |
0 |
Project Execution Plan for Building Community Centre |
1 |
Project Initiation of Execution |
1.1 |
Preparation of Project development plan |
1.2 |
Project charter presentation |
1.3 |
Project Agenda setting |
1.4 |
Finalization of project objectives |
1.5 |
Finalization of project resources |
1.6 |
Finalization of project contract signing |
2 |
Project Planning for Execution |
2.1 |
Project plan development |
2.2 |
Selection sites |
2.3 |
Preparation of contract signing |
2.4 |
Phased plan for construction |
2.5 |
Selection of contractors |
2.6 |
Construction plot booking |
2.7 |
Segmentation of areas for building centre |
3 |
Project Execution Processes |
3.1 |
Analysis of sites |
3.2 |
Storage selection |
3.3 |
design of hall |
3.4 |
Arrangements for hall |
3.5 |
Preparation in building piece of arts within hall |
3.6 |
Building of stage |
3.7 |
Garden building |
3.8 |
Construction of parking lot |
3.9 |
Building of site models |
3.10 |
Construction of Restrooms |
3.11 |
Construction of playground |
3.12 |
Construction of basket ball corner |
3.13 |
Arrangement for halls and flooding zones for guests |
4 |
Project closure |
4.1 |
Project charter sign off |
4.2 |
Final Presentation preparation |
4.3 |
Reviewing and testing of planned schedules |
4.4 |
Finalization of project phases |
4.5 |
End of project |
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
0 |
Project Execution Plan for Building Community Centre |
430 days |
01-05-2017 |
21-12-2018 |
||
1 |
Porject Initiation of Execution |
102 days |
01-05-2017 |
19-09-2017 |
||
1.1 |
Preparation of Project development plan |
30 days |
01-05-2017 |
09-06-2017 |
Project Manager ,Project Planner |
|
1.2 |
Project charter presentation |
20 days |
12-06-2017 |
07-07-2017 |
2 |
Project Manager |
1.3 |
Project Agenda setting |
10 days |
10-07-2017 |
21-07-2017 |
3 |
Project Manager |
1.4 |
Finalization of project objectives |
15 days |
24-07-2017 |
11-08-2017 |
4,3 |
Project Manager ,Project Planner |
1.5 |
Finalization of project resoruces |
13 days |
14-08-2017 |
30-08-2017 |
5 |
Project Manager |
1.6 |
Finalization of project contract signing |
14 days |
31-08-2017 |
19-09-2017 |
6 |
Project Planner |
2 |
Project Planning for Execution |
101 days |
20-09-2017 |
07-02-2018 |
||
2.1 |
Project plan development |
20 days |
20-09-2017 |
17-10-2017 |
7 |
Project Manager ,Project Planner |
2.2 |
Selection sites |
13 days |
18-10-2017 |
03-11-2017 |
9 |
Construction head ,Designer |
2.3 |
Preparation of contract signning |
15 days |
06-11-2017 |
24-11-2017 |
10,9 |
Architect ,Designer |
2.4 |
Phased plan for construction |
12 days |
27-11-2017 |
12-12-2017 |
11 |
Project sponsor ,Site engineers |
2.5 |
Selection of contractors |
16 days |
13-12-2017 |
03-01-2018 |
12 |
Clients ,Construction head |
2.6 |
Construction plot booking |
20 days |
04-01-2018 |
31-01-2018 |
13,12 |
Construction head |
2.7 |
Segmentation of areas for building centre |
5 days |
01-02-2018 |
07-02-2018 |
14 |
Designer ,Project sponsor |
3 |
Project Execution Processes |
177 days |
01-02-2018 |
05-10-2018 |
||
3.1 |
Analysis of sites |
10 days |
01-02-2018 |
14-02-2018 |
14 |
Hardware head ,Project Manager |
3.2 |
Storage selection |
12 days |
15-02-2018 |
02-03-2018 |
17 |
Construction head ,Site engineers |
3.3 |
design of hall |
15 days |
05-03-2018 |
23-03-2018 |
18 |
Designer ,Hardware head |
3.4 |
Arrangements for hall |
14 days |
26-03-2018 |
12-04-2018 |
19 |
Construction head ,Site engineers |
3.5 |
Preparation in building piece of arts within hall |
18 days |
13-04-2018 |
08-05-2018 |
20 |
Construction head ,Designer |
3.6 |
Building of stage |
12 days |
09-05-2018 |
24-05-2018 |
21 |
Site engineers |
3.7 |
Garden building |
14 days |
25-05-2018 |
13-06-2018 |
22 |
Project Planner |
3.8 |
Construction of parking lot |
13 days |
14-06-2018 |
02-07-2018 |
23 |
Construction head |
3.9 |
Building of site models |
15 days |
03-07-2018 |
23-07-2018 |
24 |
Construction head ,Designer |
3.10 |
Construction of Restrooms |
14 days |
24-07-2018 |
10-08-2018 |
25 |
Architect ,Designer ,Workers |
3.11 |
Construction of playground |
12 days |
13-08-2018 |
28-08-2018 |
26,24 |
Construction head ,Site engineers |
3.12 |
Construction of basket ball corner |
16 days |
29-08-2018 |
19-09-2018 |
27,26 |
Construction head ,Site engineers |
3.13 |
Arrangment for halls and fooding zones for guests |
12 days |
20-09-2018 |
05-10-2018 |
28 |
Construction head ,Designer |
4 |
Project closure |
55 days |
08-10-2018 |
21-12-2018 |
||
4.1 |
Project charter sign off |
12 days |
08-10-2018 |
23-10-2018 |
29 |
Project Manager ,Project Planner |
4.2 |
Final Presentatiion preparation |
10 days |
24-10-2018 |
06-11-2018 |
31 |
Project Manager |
4.3 |
Revewing and testing of planned schedules |
11 days |
07-11-2018 |
21-11-2018 |
32,29 |
Project Manager |
4.4 |
Finalization of project phases |
10 days |
22-11-2018 |
05-12-2018 |
33 |
Project Planner |
4.5 |
End of project |
12 days |
06-12-2018 |
21-12-2018 |
34 |
Project Manager |
References
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), 278-290.
Takey, S. M., & de Carvalho, M. M. (2015). Competency mapping in project management: An action research study in an engineering company. International Journal of Project Management, 33(4), 784-796.
Teller, J., & Kock, A. (2013). An empirical investigation on how portfolio risk management influences project portfolio success. International Journal of Project Management, 31(6), 817-829.
Todorovi?, M. L., Petrovi?, D. ?., Mihi?, M. M., Obradovi?, V. L., & Bushuyev, S. D. (2015). Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), 772-783.
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), 1382-1394.
Turner, R. (2016). Gower handbook of project management. Routledge.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
Williams, S., El-Rawas, O., Green, P., & Boehm, B. (2013). Learning project management decisions: A case study with case-based reasoning versus data farming.