Work Breakdown Structure
WBS |
TS for Social Media |
1 |
Initiation phase |
1.1 |
Understanding website development requirements |
1.2 |
Meeting between PM and Project Sponsor |
1.3 |
Delivering project proposal |
1.4 |
Development of Service Level Agreement |
1.5 |
Budget estimation |
1.6 |
Risk identification |
2 |
Planning phase |
2.1 |
website design development |
2.2 |
Focusing on client’s review |
2.3 |
Developing website prototype |
2.4 |
prototype modeling |
2.5 |
website verification |
2.6 |
Website validation |
2.7 |
Project approval |
2.8 |
Coding |
2.8.1 |
Template development |
2.8.2 |
Database development |
2.8.3 |
Code validation |
2.8.4 |
Browser testing |
2.8.5 |
Customization of the website |
3 |
Project execution |
3.1 |
Project content build up |
3.2 |
Website blueprint development |
3.3 |
Website development |
3.4 |
Risk management plan development |
4 |
Project closure phase |
4.1 |
Project implementation |
4.2 |
Stakeholder signoff |
Task Mode |
Task Name |
Duration |
Start |
Finish |
Auto Scheduled |
TS for SMRC |
204 days |
Thu 5/25/17 |
Tue 3/6/18 |
Auto Scheduled |
Initiation phase |
78 days |
Thu 5/25/17 |
Mon 9/11/17 |
Auto Scheduled |
Understanding website development requirements |
8 days |
Thu 5/25/17 |
Mon 6/5/17 |
Auto Scheduled |
Meeting between PM and Project Sponsor |
4 days |
Tue 6/6/17 |
Fri 6/9/17 |
Auto Scheduled |
Delivering project proposal |
16 days |
Mon 6/12/17 |
Mon 7/3/17 |
Auto Scheduled |
Development of Service Level Agreement |
13 days |
Tue 7/4/17 |
Thu 7/20/17 |
Auto Scheduled |
Budget estimation |
18 days |
Fri 7/21/17 |
Tue 8/15/17 |
Auto Scheduled |
Risk identification |
19 days |
Wed 8/16/17 |
Mon 9/11/17 |
Auto Scheduled |
Planning phase |
84 days |
Tue 9/12/17 |
Fri 1/5/18 |
Auto Scheduled |
website design development |
6 days |
Tue 9/12/17 |
Tue 9/19/17 |
Auto Scheduled |
Focusing on client’s review |
5 days |
Wed 9/20/17 |
Tue 9/26/17 |
Auto Scheduled |
Developing website prototype |
4 days |
Wed 9/27/17 |
Mon 10/2/17 |
Auto Scheduled |
prototype modeling |
5 days |
Tue 10/3/17 |
Mon 10/9/17 |
Auto Scheduled |
website verification |
7 days |
Tue 10/10/17 |
Wed 10/18/17 |
Auto Scheduled |
Website validation |
6 days |
Thu 10/19/17 |
Thu 10/26/17 |
Auto Scheduled |
Project approval |
11 days |
Fri 10/27/17 |
Fri 11/10/17 |
Auto Scheduled |
Coding |
40 days |
Mon 11/13/17 |
Fri 1/5/18 |
Auto Scheduled |
Template development |
6 days |
Mon 11/13/17 |
Mon 11/20/17 |
Auto Scheduled |
Database development |
9 days |
Tue 11/21/17 |
Fri 12/1/17 |
Auto Scheduled |
Code validation |
9 days |
Mon 12/4/17 |
Thu 12/14/17 |
Auto Scheduled |
Browser testing |
7 days |
Fri 12/15/17 |
Mon 12/25/17 |
Auto Scheduled |
Customization of the website |
9 days |
Tue 12/26/17 |
Fri 1/5/18 |
Auto Scheduled |
Project execution |
40 days |
Mon 1/8/18 |
Fri 3/2/18 |
Auto Scheduled |
Project content build up |
13 days |
Mon 1/8/18 |
Wed 1/24/18 |
Auto Scheduled |
Website blueprint development |
9 days |
Thu 1/25/18 |
Tue 2/6/18 |
Auto Scheduled |
Website development |
9 days |
Wed 2/7/18 |
Mon 2/19/18 |
Auto Scheduled |
Risk management plan development |
9 days |
Tue 2/20/18 |
Fri 3/2/18 |
Auto Scheduled |
Project closure phase |
2 days |
Mon 3/5/18 |
Tue 3/6/18 |
Auto Scheduled |
Project implementation |
1 day |
Mon 3/5/18 |
Mon 3/5/18 |
Auto Scheduled |
Stakeholder signoff |
1 day |
Tue 3/6/18 |
Tue 3/6/18 |
Figure1: Gantt chart for social Media Research center
(Source: Created by author)
Figure 2: Time phase budget for Social Media Research Center
(Source: created by author)
Name of the risk |
Type of the risk |
Impact of risk |
Frequency of the risk occurrence |
Mitigation strategy for the risk |
Data share |
Positive |
Lower |
Lower |
Though, a positive risk gives different opportunity to the organization. With the help of outsourced experts the part or the entire opportunity might get transferred or shared among the members. By developing new products the inner market might get benefitted with the help of sharing component. In order to make this product available sooner, the enterprises are required to sign either with the experts or with another organization. for mitigating this issue the company is required to hire expert team. |
Virus or worm attack |
Negative |
High |
High |
If proper security measures are not adapted then, the social media research center will be negatively affected. In order to mitigate this issue proper encryption algorithm and authentication approaches are required to be adopted. |
Data transfer issue |
Negative |
High |
High |
It might happen that during the data transfer or platform migration, any data get thefy by the external attackers. In order to mitigate this issue, the data transfer path is required to be encrypted properly. |
Software license oriented issues |
Negative |
High |
High |
In order to run the website properly, proper software license are required to be installed by social media research center. The overall rate of cost and resource allocation issues will be completely mitigated after the adaptation of proper software license. |
Quality management plan
It has been found that for gaining commercial profit and competitive advantages from the competitive marketplace, Social media Research Center is required to develop a secured as well as easy website for their consumers. Moreover, the website is needed to be secured from the external attackers. Therefore, the company must focus on developing a consumer focused website that could be accessed by the developers regardless of their location and time as well. The website should maintain the standard of the Graphical User Interface (GUI). For securing the website from the digital assaults security is the main concern that is required to be considered by the system infrastructure management authority of Social Media Research Center.
Product quality assurance
The product and quality are the two major aspects that are needed to be considered by any business organization for assuring their commercial profit from the competitive marketplace. For managing large set of information regarding both personnel information and official data the quality of the website is needed to be very much consumer focused. Even the revenue to the company is also dependent on the quality and number of the consumers of the company. Moreover, if the company fails to meet the requirement of the clients then the entire web application development project will be a failure. Before developing the business plan the project manager and the application programming manager should focus on the strategy of consumer centric business. Even, while developing such project, continuous monitoring and control are required to be followed by the management authority of social Media Research Center.
Quality control plan
Quality control is the last phase of quality control management planning. In this phase, the authority is required to adopt various project control measures for securing the website from the external attackers. The object should be a shared one and the project team members including the project manager must focus on the quality of the project. In order to grab more number of consumers throughout it is necessary to monitor the project progress properly considering the project budget and time for the project completion. After considering the project components it has been found that, for the successful completion of the project, $50,000 AUD and 8months are required. Even, the project manager should, estimate extra budget so that whenever required they could efficiently relevant resources. It is determined that the commercial benefit of the project is dependent on both the external and internal features of the website. The website must maintain all the golden rules of responsive web design approach.
For successful completion of the project the project manager should maintain all the project development phases accurately. The phases of project development include project initiation, project planning, project execution and project closure. The project closure checklist is consists of different components and the components are as follows:
- The project is required to be completed within the estimated budget that is $50,000 AUD.
- The project should be completed within8 months
- The project sponsor should select the most suitable project sponsors for the project.
- The common project standards should be maintained by the project manager and he or must think about to exceed the standard.
- The project team members must estimate accurate payment requirement.
- Before implementation of the project the manager should, develop a prototype so that they could make the change as per the wish of the consumers.
- Before the implementation of the project the manager should provide approval to the project development team.
- In the project closure phase al the stakeholders should signoff the project.
Gantt chart for social media research center
Baptista, A., Santos, F., Páscoa, J., & Sändig, N. (2016). Project Management Methodologies as Main Tool for Current Challenges in Global Economy Driving Historical Changes. Journal of Advanced Management Science Vol, 4(2).
Chan, B. W. H., & Lei, C. T. (2016). Development and Validation of Project Management Constructs of Security Door Access Control Systems: A Pilot Study in Macau. Nang Yan Business Journal, 4(1), 23-43.
Chaves, M. S., Araújo, C. D., Teixeira, L., Rosa, D., Júnior, I., & Nogueira, C. (2016). A new approach to managing Lessons Learned in PMBoK process groups: the Ballistic 2.0 Model. International Journal of Information Systems and Project Management, 4(1), 27-45.
Ferreira, F., Marques, A. L., Faria, J., & Azevedo, A. (2016). Large project management in the automotive industry: a flexible and knowledge based approach. In New Advances in Information Systems and Technologies (pp. 455-464). Springer International Publishing.
Garcia, I., Pacheco, C., Arcilla, M., & Sanchez, N. (2016). Project Management in Small-Sized Software Enterprises: A Metamodeling-Based Approach. In Trends and Applications in Software Engineering (pp. 3-13). Springer International Publishing.
Golini, R., Corti, B., & Landoni, P. (2017). More efficient project execution and evaluation with logical framework and project cycle management: evidence from international development projects. Impact Assessment and Project Appraisal, 35(2), 128-138.
Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt Assn.
Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
KhodaBandehLou, A., Parvishi, A., Taghifam, R., Lotfi, M., & Taleei, A. (2016). Integrating earned value management with risk management to control the time-cost of the project. Iioab journal, 7, 114-119.
Landry, J., & McDaniel, R. (2016). Agile Preparation Within a Traditional Project Management Course. Information Systems Education Journal, 14(6), 27.
Lannon, J., & Walsh, J. (2016). Guest Editorial: Reinvigorating Project Management Research and Practice: Perspectives from the Non-Profit Sector. Project Management Research and Practice, 3, 5119.
Lock, M. D. (2014). The essentials of project management. Ashgate Publishing, Ltd..
Mahmoud-Jouini, S. B., Midler, C., & Silberzahn, P. (2016). Contributions of Design Thinking to Project Management in an Innovation Context. Proj Mgmt Jrnl, 47, 144-156.
Markovic, G., Mihi?, M., & Obradovic, V. (2015). Implementation of project management concept into industrial energetics: Case study in paper factory. Management, 75.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International Journal of Project Management, 32(2), 202-217.
Paquin, J. P., Gauthier, C., & Morin, P. P. (2016). The downside risk of project portfolios: The impact of capital investment projects and the value of project efficiency and project risk management programmes. International Journal of Project Management, 34(8), 1460-1470.
Richard, H. A., Sorooshian, S., & Shariman, M. (2016). Lean Construction: An Effective Approach for Project Management. ARPN Journal of Engineering and Applied Sciences, 11(3), 1607-1612.
Saltz, J., & Crowston, K. (2017, January). Comparing Data Science Project Management Methodologies via a Controlled Experiment. In Proceedings of the 50th Hawaii International Conference on System Sciences.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Su, C. M., Chang, K. Y., & Chang, Y. H. (2016). Applying Possibilistic Linear Programming to Multi-objective New Ship of Sign on Proceeding Project Management Problem. In Proceedings of the International MultiConference of Engineers and Computer Scientists (Vol. 2).
Suetin, S., Vikhodtseva, E., Nikitin, S., Lyalin, A., & Brikoshina, I. (2016, January). Results of agile project management implementation in software engineering companies. In ITM Web of Conferences (Vol. 6). EDP Sciences.
Turner, R. (2016). Gower handbook of project management. Routledge.
Vanhoucke, M., Coelho, J., & Batselier, J. (2016). An overview of project data for integrated project management and control. Journal of Modern Project Management, 3(2), 6-21.
Zwikael, O. (2016). International journal of project management special issue on “project benefit management”.