Project Start-Up Activities
Discuss about the International Journal Of Modern Education Forum.
The following assessment is developed using the implication of the improved functional analysis. The project of “installing new network” server would be eased by the utilization of the operations depicting the utilization of the proposal. The development would also be formed for easing the implication of the successive deployment of the operations and listing the specific formation. The utilization of the activities would support the alignment of the improved communication and development (Taghavifard, Amiri and Sharifian 2015). The topics of project start up activities, project implementation, project integration, and project follow up activities would be explained in this assignment.
The network development project start up activities would comprise of the implication of the improved functional development and operations. The network development project start up activities would comprise of forming the alignment of the operations and deployment of the successive activity development (Samerkhanova et al. 2016). The consultation with the network development project stakeholders would be deployed for easing the process of the facility development. The initiation activities of the network development project would comprise of forming the significant utilization of the network development project operations. The review of the existing network development project activities would align with the significant development of the operations that are aligned with the implication of the initial network development project operations (Zhang, Jia and Diaz 2015). The network development project start up would be supported by the alignment of the facilities developing the alignment of the initialization of the network development project.
The network development project initialization is based on the alignment of the activities and using waterfall model for initiation. The deployment of the operations would be helpful for easing the processing of the improved architecture and development (Redchenko 2016). The initialization of the network development project activities would comprise of the development of initial network development project development. The network development project start-up activities would be based on the implication of processes supplying with the alignment of the successful implication development. The implication of the successful activities would be developed for easing the implication of the proposed network development project initiation activities.
The network development project initiation involves the implication of the activities supporting the utilization of the improved network development project implication development. The various roles and responsibilities of the network development project team members would be included for the alignment of the improved functional alignment (van Kollenburg et al. 2017). The support and network development project plan development would be helpful for analysing the implication of successive development. The network development project manager is responsible for the execution of the improved activities for developing the final network development project execution. The deployment would be supported by the formation of the activities for aligning with the implication of the improved operation development.
Project Implementation
The management of the resources for the implication would be deployed for easing the utilization of the proper alignment of the network development resources so that alignment would be implied for the modification of the improved functional development (Hasegawa 2014). The resource management for the improved project initialization would be based on the alignment of the improved functional and support development. The scheduling of the “Network Infrastructure Project” is given below,
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Network Infrastructure Development Project |
70 days |
Mon 7/23/18 |
Fri 10/26/18 |
1 |
Project Start up Activities |
8 days |
Mon 7/23/18 |
Wed 8/1/18 |
1.1 |
Requirement Analysis |
2 days |
Mon 7/23/18 |
Tue 7/24/18 |
1.2 |
Developing initial documents |
3 days |
Wed 7/25/18 |
Fri 7/27/18 |
1.3 |
Submission of documents |
2 days |
Mon 7/30/18 |
Tue 7/31/18 |
1.4 |
Sign up |
1 day |
Wed 8/1/18 |
Wed 8/1/18 |
1.5 |
Kick off |
0 days |
Wed 8/1/18 |
Wed 8/1/18 |
2 |
Project Implementation |
22 days |
Thu 8/2/18 |
Fri 8/31/18 |
2.1 |
Planning |
11 days |
Thu 8/2/18 |
Thu 8/16/18 |
2.1.1 |
Planning Methodology is selected |
1 day |
Thu 8/2/18 |
Thu 8/2/18 |
2.1.2 |
Plan Outline |
2 days |
Fri 8/3/18 |
Mon 8/6/18 |
2.1.3 |
Review of Plan |
3 days |
Tue 8/7/18 |
Thu 8/9/18 |
2.1.4 |
Complete Plan Development |
5 days |
Fri 8/10/18 |
Thu 8/16/18 |
2.1.5 |
Plan Approval |
0 days |
Thu 8/16/18 |
Thu 8/16/18 |
2.2 |
Design |
11 days |
Fri 8/17/18 |
Fri 8/31/18 |
2.2.1 |
Network Design Platform |
1 day |
Fri 8/17/18 |
Fri 8/17/18 |
2.2.2 |
Design Outline |
2 days |
Mon 8/20/18 |
Tue 8/21/18 |
2.2.3 |
Review of Design |
3 days |
Wed 8/22/18 |
Fri 8/24/18 |
2.2.4 |
Complete Design Development |
5 days |
Mon 8/27/18 |
Fri 8/31/18 |
2.2.5 |
Design Approval |
0 days |
Fri 8/31/18 |
Fri 8/31/18 |
3 |
Project Integration |
28 days |
Mon 9/3/18 |
Wed 10/10/18 |
3.1 |
Hardware Installation |
7 days |
Mon 9/3/18 |
Tue 9/11/18 |
3.2 |
Software Programming |
6 days |
Wed 9/12/18 |
Wed 9/19/18 |
3.3 |
Basic Infrastructure is developed |
10 days |
Thu 9/20/18 |
Wed 10/3/18 |
3.4 |
Backup and disaster recovery planning |
5 days |
Thu 10/4/18 |
Wed 10/10/18 |
3.5 |
System Developed |
0 days |
Wed 10/10/18 |
Wed 10/10/18 |
4 |
Project Follow up Activities |
12 days |
Thu 10/11/18 |
Fri 10/26/18 |
4.1 |
Maintenance plan is developed |
3 days |
Thu 10/11/18 |
Mon 10/15/18 |
4.2 |
Execution of maintenance plan |
5 days |
Tue 10/16/18 |
Mon 10/22/18 |
4.3 |
Final reports are made |
2 days |
Tue 10/23/18 |
Wed 10/24/18 |
4.4 |
submission of documents |
1 day |
Thu 10/25/18 |
Thu 10/25/18 |
4.5 |
sign up |
1 day |
Fri 10/26/18 |
Fri 10/26/18 |
4.6 |
Closure |
0 days |
Fri 10/26/18 |
Fri 10/26/18 |
The Gantt chart would be helpful for the development of the effective project initiation plan and aligning the activities successfully for the completion of the project. The alignment of the improved project completion would be helpful for forming the analysis of the successive project completion. The implication of the smart project development would support the formation of the project analysis and development.
The implementation of the “Network Infrastructure Project” would be supported by the conflict resolution plan. The conflict management would help in managing the installation of the improved network infrastructure for the organization (Abolmasov et al. 2017). The resolution of the conflicts would support the utilization of the operations and deployment of the effective functional analysis.
The change management is helpful for enlisting the utilization of the operations that are successively deployed for the project execution and it would require the management of the changes in the project effectively (Lazarev 2015). The support and development of the factors of project functions can be aligned for the utilization of the improved functional and development factors.
The project manager is responsible for ensuring that the project is completed successfully and the required leadership qualities for the project of “Network Infrastructure Project” include understanding of the requirements, good communication skills, providing encouragement, and project planning skills.
The aligning with the project plan would be based on the implication of the effective project initiation documents. The support and development of the activities would be aligned with the implication of the operations taking care of the functions of the plan development and execution.
The effective plan development would support to the utilization of the smart project development factors that would help in taking care of the execution information transfer. According to van Kollenburg et al. (2017), the inclination of the project development can take care of the factors that are formed for ensuring that the project can be executed for the development factors. The communication would support the transfer of the information that can provide the support required for the project.
Project Integration
The “Network Infrastructure Project” would require the construction of the project activities and aligning it with the implication of the operations. The integration would be developed for forming the inclusion of the activities for easing the utilization of the project integration planning (Redchenko 2016). The activities of the project plan would be aligned with the development of the operations so that the alignment can be formed for the support and development. The regular and constant measurement would be helpful for using the utilization of the support and development.
The consultation and report mechanism would be helpful for integrating the project activities and form a constant check for the completion of the project (Samerkhanova et al. 2016). The external consultant is needed for the project of “Network Infrastructure Project” so that the factors can be aligned effectively. It would also ensure that the project might be helpful for executing the improved alignment.
The project activities would be helpful for forming the differentiation of the operations and alignment of the support and development for the effective project execution (Taghavifard, Amiri and Sharifian 2015). The monitoring of the activities would endure the utilization of the factors supporting the formation of the improved alignment and development.
The project follow-up activities of “Network Infrastructure Project” would involve the analysis of the final deliverables based on the requirements of the clients. The final report would include the final specification of the network server developed and its working test results. The client can analyse it and form the implication of the final project execution.
The network infrastructure would have impact on the working culture of the organization for which the structure is developed (Taghavifard, Amiri and Sharifian 2015). The simplification of the factors of the project analysis can be formed with the simplification and utilization of the proper project execution.
The IT network administration team would be required for ensuring all required tests for the working functionality of the network infrastructure would be checked (Zhang, Jia and Diaz 2015). The appropriate analysis would mark the simplification of the factors in case of the appropriate implication of the tools. The testing team would be required for dealing with the support and development of the network functions for “Network Infrastructure Project”.
Conclusion
The project of “installing new network” server had been eased by the utilization of the operations depicting the utilization of the proposal. The development had been formed for easing the implication of the successive deployment of the operations and listing the specific formation. The utilization of the activities would support the alignment of the improved communication and development. The topics of project start up activities, project implementation, project integration, and project follow up activities had been explained in this assignment.
References
Abolmasov, B., Damjanovi?, D., Marjanovi?, M., Stankovi?, R., Nikoli?, V., Nedeljkovi?, S. and Petrovi?, Ž., 2017, May. Project BEWARE—Landslide Post-disaster Relief Activities for Local Communities in Serbia. In Workshop on World Landslide Forum (pp. 413-422). Springer, Cham.
Hasegawa, M., 2014, November. New education scheme for college students through out-of-curriculum project activities. In International Journal of Modern Education Forum (Vol. 3, No. 4).
Lazarev, V., 2015. Project Activities at School: Unused Opportunities. Educational Studies, (3), pp.292-307.
Redchenko, N.N., 2016. Project Activities as a Form of English Language Teaching Based on the Interdisciplinary Approach to Form Intercultural Communicative Competence. International Journal of Environmental and Science Education, 11(13), pp.6203-6211.
Samerkhanova, E.K., Krupoderova, E.P., Krupoderova, K.R., Bahtiyarova, L.N. and Ponachugin, A.V., 2016. Students’ Network Project Activities in the Context of the Information Educational Medium of Higher Education Institution. International Journal of Environmental and Science Education, 11(11), pp.4578-4586.
Taghavifard, M.T., Amiri, M. and Sharifian, M.E., 2015. A MULTI-OBJECTIVE MODEL TO MINIMIZE TIME AND UNLIMITED MULTI RESOURCE LEVELING IN MULTI-MODE PROJECT ACTIVITIES. International Journal of Academic Research, 7.
van Kollenburg, J., Bogers, S., Deckers, E., Frens, J. and Hummels, C., 2017, May. How Design-inclusive UXR Influenced the Integration of Project Activities: Three Design Cases from Industry. In Proceedings of the 2017 CHI Conference on Human Factors in Computing Systems (pp. 1408-1418). ACM.
Zhang, J., Jia, S. and Diaz, E., 2015. A new buffer sizing approach based on the uncertainty of project activities. Concurrent Engineering, 23(1), pp.3-12.